107634 | Media Borough Pedestrian Enhancements(L)© (Delaware County)
This project will complete gaps in sidewalk network throughout the borough.
12/8/2022--Project Let, District control has been changed from EE/DVRPC/D. Snyder to CONSTR. Low bidder was Premier Concrete, Inc. with a low bid amount of $684,746.25.
Limits: Media Borough
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | CAQ | $790 | $0 | $0 | $0 | $0 |
Program Year Totals: | $790 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $790 | Total FY23-FY34 Cost: | $790 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Let | 2022-12-08 |
CON | Phase on Approved STIP | |
CON | Award Contract | 2023-01-07 |
CON | Start of Phase | 2023-02-06 |
CON | Notice to Proceed | 2023-03-06 |
CON | Physical Work Complete | 2023-05-14 |
CON | Project Agreement End Date | 2024-05-19 |
CON | Completion of Phase | 2024-09-23 |