107554 | US30 & PA82 Interchange Improvement (West Caln Township & Valley Township, Chester County)

The planned SR 82 Interchange project (US 30, Section 082) is being undertaken in conjunction with corridor wide improvements planned for the 14.5-mile US 30 Coatesville – Downingtown Bypass. The project extends along US 30 from approximately 0.2 miles east of Wagontown Road in Valley Township to 0.1 miles west of the SR 340 bridge over US 30 in Caln Township. Planned work will consist of the full reconstruction of US 30 to upgrade the existing roadway which is approaching the end of its serviceable life. Reconfiguration of the interchange with SR 82 will be undertaken to address substandard acceleration/deceleration ramp lengths and poor geometry of the westbound exit ramp. The project will also address deficient median conditions, shoulder widths and the functionally obsolete bridges (US 30 over W. Brandywine Creek, US 30 over SR 82, & US 30 over Moore Road) within the project limits. Reconfiguration of the SR 82/SR 340 intersection will also be undertaken as part of the project to improve movement through the intersection. No additional travel lanes are proposed on any of the roadways involved in the project.
This is a breakout of MPMS #84884.

Limits: 0.2 miles east of Wagontown Rd in Valley to 0.1 miles west of SR 340 bridge o/ US 30 in Caln
Air Quality Code: R3

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDNHPP$0$0$3113$3113$0
FD581$0$778$778$778$0
FDSTU$0$3113$0$0$0
ROWNHPP$0$0$0$0$10916
ROW581$0$0$0$0$2730
UTLNHPP$0$0$0$0$3284
UTL581$0$0$0$0$820
CONSTU$0$0$0$0$10000
CONNHPP$0$0$0$0$105820
CONSPK-NHPP$0$0$0$0$30000
CON581$0$0$0$0$36453
Program Year Totals:$0$3,891$3,891$3,891 
Total FY23-FY26 Cost:$11,673Total FY23-FY34 Cost:$211,696 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase Approved by PMC
ROWStart of Phase2020-09-01
UTLStart of Phase2020-09-01
FDPhase on Approved STIP
FDStart of Phase2023-10-01
UTLPlan to Utility Unit2024-05-15
ROWPlan to ROW Unit2024-08-15
UTLCompletion of Phase2025-09-01
ROWCompletion of Phase2025-09-01
FDPS+E to District Contract Management2026-11-15
CONLet2027-12-09
CONAward Contract2028-01-08
FDCompletion of Phase2028-02-07
CONStart of Phase2028-02-07
CONNotice to Proceed2028-02-07
CONPhysical Work Complete2029-02-26
CONCompletion of Phase2029-04-27
CONProject Agreement End Date2030-08-27