104879 | Cheyney Road Bridge Replacement (Delaware County)
This project involves the replacement of the state-owned bridge located on Cheyney Road over a branch of the Chester Creek in Thornbury Township, Delaware County. The existing bridge, built in 1931, is a one-span reinforced concrete slab structure with a span length of 10 feet. The bridge is two lanes wide with no shoulders or sidewalk. The existing structure will be replaced, and guiderail, traffic signs, and delineators will be installed as required.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or
state Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 185 | $113 | $0 | $0 | $0 | $0 |
ROW | 185 | $17 | $0 | $0 | $0 | $0 |
ROW | STU | $67 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $0 | $49 | $0 |
CON | STU | $0 | $0 | $0 | $492 | $0 |
CON | 185 | $0 | $0 | $0 | $123 | $0 |
Program Year Totals: | $197 | $0 | $0 | $664 | ||
Total FY23-FY26 Cost: | $861 | Total FY23-FY34 Cost: | $861 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Start of Phase | 2019-10-01 |
ROW | Start of Phase | 2020-10-01 |
FD | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2023-02-11 |
UTL | Plan to Utility Unit | 2023-06-01 |
ROW | Plan to ROW Unit | 2023-06-01 |
UTL | Completion of Phase | 2023-11-27 |
ROW | Completion of Phase | 2023-11-27 |
FD | PS+E to District Contract Management | 2024-06-15 |
CON | Let | 2024-09-26 |
CON | Award Contract | 2024-10-26 |
CON | Notice to Proceed | 2024-11-25 |
FD | Completion of Phase | 2024-11-25 |
CON | Start of Phase | 2024-11-25 |
CON | Physical Work Complete | 2025-11-28 |
CON | Completion of Phase | 2026-01-27 |
CON | Project Agreement End Date | 2027-05-29 |