104343 | US 322 over CSX (Bridge) (Upper Chichester Township, Delaware County)
Replacement of the bridge carrying SR 322 over CSX and Bethel Road as well as improvements to the Bethel Road Interchange.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: I-95 Interchange to PA 452 Interchange
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | STP | $0 | $0 | $10000 | $0 | $0 |
CON | BRIP | $0 | $0 | $0 | $6659 | $4715 |
CON | NHPP | $12099 | $10263 | $2099 | $2561 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $12,099 | $10,263 | $12,099 | $9,220 | ||
Total FY23-FY26 Cost: | $43,681 | Total FY23-FY34 Cost: | $48,396 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Final Utility Clearance | 2022-12-31 |
CON | Award Contract | 2023-05-14 |
CON | Start of Phase | 2023-06-13 |
CON | Notice to Proceed | 2023-06-13 |
CON | Let | 2023-11-02 |
CON | Completion of Phase | 2024-08-31 |
CON | Physical Work Complete | 2027-09-16 |
CON | Project Agreement End Date | 2029-03-16 |