❮ Back

103217 | Main Street Grade Crossing (Darby Borough, Delaware County)

The Main Street-CSX rail line grade crossing (US DOT #140641S) in Darby Borough needs to be updated and may include improvements such as new gates, lights, traffic signals (if warranted), drainage, and improvements to the crossing surface and roadway for all users at and around the grade crossing. This grade crossing currently poses significant safety concerns as it accommodates train traffic from a major interstate freight line throughout the day, vehicular traffic from two roads (Main St. and Sixth St.), and pedestrian traffic from nearby schools and retail establishments. Adding to the crossing’s complexity is SEPTA’s trolley route 11 that operates within the Main St. cartway and bisects the freight rail line (with trolley stops located on both sides of the grade crossing). The grade crossing was the subject of a two phase study conducted by DVRPC and overseen by a broad-based steering committee (see DVRPC publication #11012 and #12014).
This project was selected from the 2015 Pennsylvania Statewide Rail-Highway Grade Crossing Program for $337,653 RRX funds.

Limits: Between 5th and 7th Streets
Air Quality Code: S8

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD581$340$0$0$0$0
CONFRA$1000$0$0$0$0
CONSTU$2172$1000$2000$0$0
CONLOC$250$0$0$0$0
CONRRX$369$0$0$0$0
CONSTP$193$0$0$0$0
CONTOLL$0$0$0$0$0
Program Year Totals:$4,324$1,000$2,000$0 
Total FY23-FY26 Cost:$7,324Total FY23-FY34 Cost:$7,324 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
FDPhase Approved by PMC
FDStart of Phase2018-05-26
FDPhase on Approved STIP
CONPhase on Approved STIP
FDPS+E to District Contract Management2023-05-24
CONLet2023-08-24
CONAward Contract2023-09-15
FDCompletion of Phase2023-10-14
CONStart of Phase2023-10-14
CONNotice to Proceed2023-10-14
CONPhysical Work Complete2024-08-23
CONCompletion of Phase2024-10-22
CONProject Agreement End Date2026-02-21