102664 | PA309 over Beaver Run (Bridge) (Richland Township, Bucks County)
This project involves rehabilitating or replacing the Bridge at PA309 over Beaver Run. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | 185 | $0 | $250 | $0 | $0 | $0 |
FD | 185 | $0 | $0 | $0 | $0 | $600 |
ROW | 185 | $0 | $0 | $0 | $0 | $250 |
UTL | 185 | $0 | $0 | $0 | $0 | $250 |
CON | 185 | $0 | $0 | $0 | $0 | $4000 |
Program Year Totals: | $0 | $250 | $0 | $0 | ||
Total FY23-FY26 Cost: | $250 | Total FY23-FY34 Cost: | $5,350 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Start of Phase | |
ROW | Start of Phase | 2022-06-06 |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
ROW | Completion of Phase | 2023-05-31 |
UTL | Completion of Phase | 2023-05-31 |
PE | N. E. P. A. Approval | 2023-06-30 |
PE | Completion of Phase | 2023-07-30 |
FD | Start of Phase | 2023-07-30 |
UTL | Start of Phase | 2024-01-30 |
ROW | Plan to ROW Unit | 2024-06-30 |
UTL | Plan to Utility Unit | 2024-06-30 |
FD | PS+E to District Contract Management | 2026-06-30 |
CON | Let | 2026-12-10 |
CON | Award Contract | 2027-01-09 |
CON | Notice to Proceed | 2027-02-08 |
CON | Start of Phase | 2027-02-08 |
FD | Completion of Phase | 2027-02-08 |
CON | Physical Work Complete | 2028-12-30 |
CON | Completion of Phase | 2029-02-28 |
CON | Project Agreement End Date | 2030-06-30 |