102309 | PA 309 over Morgan Creek (Richland Township, Bucks County)
This project involves rehabilitating or replacing the Bridge at PA 309 over Morgan Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | STU | $50 | $200 | $0 | $0 | $0 |
FD | 185 | $0 | $0 | $0 | $0 | $712 |
ROW | 185 | $0 | $0 | $0 | $0 | $346 |
UTL | 185 | $0 | $0 | $0 | $0 | $346 |
CON | 185 | $0 | $0 | $0 | $0 | $5537 |
Program Year Totals: | $50 | $200 | $0 | $0 | ||
Total FY23-FY26 Cost: | $250 | Total FY23-FY34 Cost: | $7,191 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase on Approved STIP | |
PE | Start of Phase | 2018-10-17 |
ROW | Completion of Phase | 2019-05-31 |
ROW | Start of Phase | 2022-06-06 |
UTL | Start of Phase | 2022-06-06 |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
PE | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
UTL | Completion of Phase | 2023-05-31 |
PE | N. E. P. A. Approval | 2023-06-30 |
PE | Completion of Phase | 2023-07-30 |
FD | Start of Phase | 2023-07-30 |
UTL | Plan to Utility Unit | 2024-06-30 |
ROW | Plan to ROW Unit | 2024-06-30 |
FD | PS+E to District Contract Management | 2025-06-30 |
CON | Let | 2026-12-15 |
CON | Award Contract | 2027-01-14 |
FD | Completion of Phase | 2027-02-13 |
CON | Notice to Proceed | 2027-02-13 |
CON | Start of Phase | 2027-02-13 |
CON | Physical Work Complete | 2029-01-02 |
CON | Completion of Phase | 2029-03-03 |
CON | Project Agreement End Date | 2030-07-03 |