102272 | Holland Road at Buck Road and Route 532 (Northampton Township, Bucks County)

This project will be broken out into two phases when appropriate. Phase I is the replacement/rehabilitation of the poor condition Buck Road Bridge over Mill Creek with a wider structure to accommodate turning lanes and will also include improvements to the Buck Road/Old Bristol Road Intersection. Phase II will consist of improvements including the realignment of the Buck Road/Holland Road intersection and the addition of turning lanes, along with access management and the addition of sidewalks throughout corridor.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or
state Categorical Exclusion clearance.

Limits: Buck Rd from 1,200' south of intersection w/Old Bristol Rd to 1,500' north of intersection w/Holland
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FD581$60$0$0$0$0
ROW581$241$0$200$0$0
CON185$0$0$0$100$17038
Program Year Totals:$301$0$200$100 
Total FY23-FY26 Cost:$601Total FY23-FY34 Cost:$17,639 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
FDStart of Phase2019-10-01
CONPhase on Approved STIP
ROWPhase on Approved STIP
FDPhase on Approved STIP
ROWStart of Phase2022-10-31
ROWPlan to ROW Unit2023-03-15
ROWCompletion of Phase2023-10-31
FDPS+E to District Contract Management2024-03-14
CONLet2024-06-20
CONAward Contract2024-07-20
CONStart of Phase2024-08-19
CONNotice to Proceed2024-08-19
FDCompletion of Phase2024-08-19
CONPhysical Work Complete2028-07-03
CONCompletion of Phase2028-09-01
CONProject Agreement End Date2030-01-01