❮ Back

99668 | PA 291 Drainage Improvement (Ridley Township, Delaware County)

This project will fund drainage improvements on PA 291 from the bridge over Crum Creek to the bridge over Darby Creek, including the installation of new inlets and pipes, and construction of ditches to alleviate the existing flooding of the roadway. The existing pavement will be milled and overlaid. Base repairs will be completed as necessary to repair damage to the roadway from previous flooding.
PennDOT will acquire land in the project area for the future location of a multiuse trail for the East Coast Greenway and September 11th Memorial Trail.
This road segment is included in the Delaware County Bicycle Plan.

Limits: Between Crum Creek and Darby Creek
Air Quality Code: X13

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FD581$844$0$0$0$0
ROW581$90$0$0$0$0
UTL581$0$61$0$0$0
CON581$0$1200$2450$2450$2475
Program Year Totals:$934$1,261$2,450$2,450 
Total FY25-FY28 Cost:$7,095Total FY25-FY36 Cost:$9,570 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLPhase Approved by PMC
ROWPhase Approved by PMC
FDPhase Approved by PMC
ROWStart of Phase2018-10-01
UTLStart of Phase2018-10-01
UTLCompletion of Phase2019-09-30
ROWCompletion of Phase2019-09-30
CONPhase Approved by PMC
FDStart of Phase2022-01-15
UTLPhase on Approved STIP
FDPhase on Approved STIP
CONPhase on Approved STIP
ROWPhase on Approved STIP
ROWPlan to ROW Unit2023-07-31
FDPS+E to District Contract Management2023-07-31
UTLPlan to Utility Unit2023-07-31
FDCompletion of Phase2023-09-11
CONLet2024-10-24
CONAward Contract2024-11-23
CONStart of Phase2024-12-23
CONNotice to Proceed2024-12-23
CONPhysical Work Complete2025-10-24
CONCompletion of Phase2025-12-23
CONProject Agreement End Date2027-04-24