99668 | PA 291 Drainage Improvement (Ridley Township, Delaware County)
This project will fund drainage improvements on PA 291 from the bridge over Crum Creek to the bridge over Darby Creek, including the installation of new inlets and pipes, and construction of ditches to alleviate the existing flooding of the roadway. The existing pavement will be milled and overlaid. Base repairs will be completed as necessary to repair damage to the roadway from previous flooding.
PennDOT will acquire land in the project area for the future location of a multiuse trail for the East Coast Greenway and September 11th Memorial Trail.
This road segment is included in the Delaware County Bicycle Plan.
Limits: Between Crum Creek and Darby Creek
Air Quality Code: X13
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $844 | $0 | $0 | $0 | $0 |
ROW | 581 | $90 | $0 | $0 | $0 | $0 |
UTL | 581 | $0 | $61 | $0 | $0 | $0 |
CON | 581 | $0 | $1200 | $2450 | $2450 | $2475 |
Program Year Totals: | $934 | $1,261 | $2,450 | $2,450 | ||
Total FY25-FY28 Cost: | $7,095 | Total FY25-FY36 Cost: | $9,570 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Start of Phase | 2018-10-01 |
UTL | Start of Phase | 2018-10-01 |
UTL | Completion of Phase | 2019-09-30 |
ROW | Completion of Phase | 2019-09-30 |
CON | Phase Approved by PMC | |
FD | Start of Phase | 2022-01-15 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-07-31 |
FD | PS+E to District Contract Management | 2023-07-31 |
UTL | Plan to Utility Unit | 2023-07-31 |
FD | Completion of Phase | 2023-09-11 |
CON | Let | 2024-10-24 |
CON | Award Contract | 2024-11-23 |
CON | Start of Phase | 2024-12-23 |
CON | Notice to Proceed | 2024-12-23 |
CON | Physical Work Complete | 2025-10-24 |
CON | Completion of Phase | 2025-12-23 |
CON | Project Agreement End Date | 2027-04-24 |