98230 | Tabor Road over Tacony Creek (Bridge) (Philadelphia City)
This project is a bridge rehabilitation/replacement of Tabor Road over Tacony Creek in the City of Philadelphia.
The bridge carrying Tabor Road over Tacony Creek is a three span, non-composite, adjacent box beam bridge that was built in 1957. Anticipated work includes demolition and replacement of the superstructure; rehabilitation of the existing reinforced concrete abutments, wingwalls, and piers; full depth pavement reconstruction of the bridge approaches; replacement of the parapet, railing, curb and sidewalk; reconstruction of ADA curb ramps; coordinated relocation of utility facilities; and other miscellaneous construction. Construction will be staged, allowing the bridge to remain open for traffic and avoiding the need for a lengthy detour. Temporary pedestrian and multi-use trail detours may be required.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a component of the County Bridge Line Item (MPMS #95447).
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | 183 | $554 | $409 | $409 | $308 | $1168 |
CON | STU | $0 | $0 | $0 | $0 | $3168 |
CON | BRIP | $0 | $0 | $1634 | $0 | $0 |
CON | STP | $2215 | $1634 | $0 | $1234 | $2000 |
CON | LOC | $138 | $102 | $102 | $77 | $323 |
Program Year Totals: | $2,907 | $2,145 | $2,145 | $1,619 | ||
Total FY25-FY28 Cost: | $8,816 | Total FY25-FY36 Cost: | $15,475 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2017-02-10 |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Award Contract | 2022-09-21 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2022-10-15 |
CON | Start of Phase | 2022-10-19 |
FD | Completion of Phase | 2022-10-19 |
CON | Notice to Proceed | 2022-10-19 |
FD | PS+E to District Contract Management | 2023-12-15 |
CON | Let | 2024-04-25 |
CON | Physical Work Complete | 2025-11-28 |
CON | Completion of Phase | 2026-10-31 |
CON | Project Agreement End Date | 2027-05-29 |