98229 | 59th Street over AMTRAK (Bridge) (Philadelphia City)

This project is a bridge replacement of 59th Street over AMTRAK in the City of Philadelpia.
The current structure was built in 1926, and consists of a four simple-span, partially concrete-encased-steel girder/floorbeam/jackarch superstructure atop reinforced concrete abutment and pier substructures. The anticipated work includes demolition and removal of the existing superstructure and portions of the existing reinforced concrete abutments & piers and construction of a new steel multi-girder bridge with reinforced concrete composite deck atop reinforced concrete abutments and piers; as well as roadway approach reconstruction and repaving, curb and sidewalk reconstruction, a new high-quality bicycle facility, streetlighting improvements, ADA accessibility improvements, railroad electric traction (ET) system modification and utility relocations, and other related work.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a component of the County Bridge Line Item (MPMS #95447).

Limits: 59th Street over AMTRAK
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
UTLLOC$477$1145$0$0$0
UTLBOF$1906$4578$0$0$0
CONBOF$1918$2973$5192$7954$15474
CONLOC$120$186$324$497$967
CON183$360$557$973$1491$2901
Program Year Totals:$4,781$9,439$6,489$9,942 
Total FY25-FY28 Cost:$30,651Total FY25-FY36 Cost:$49,993 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
UTLPhase Approved by PMC
UTLStart of Phase2021-06-17
UTLCompletion of Phase2021-12-30
FDPhase on Approved STIP
CONPhase on Approved STIP
UTLPhase on Approved STIP
FDStart of Phase2023-03-17
UTLPlan to Utility Unit2023-05-05
FDPS+E to District Contract Management2024-06-15
CONLet2025-04-24
CONAward Contract2025-05-24
FDCompletion of Phase2025-06-23
CONStart of Phase2025-06-23
CONNotice to Proceed2025-06-23
CONPhysical Work Complete2026-06-25
CONCompletion of Phase2026-08-24
CONProject Agreement End Date2027-12-24