98229 | 59th Street over AMTRAK (Bridge) (Philadelphia City)
This project is a bridge replacement of 59th Street over AMTRAK in the City of Philadelpia.
The current structure was built in 1926, and consists of a four simple-span, partially concrete-encased-steel girder/floorbeam/jackarch superstructure atop reinforced concrete abutment and pier substructures. The anticipated work includes demolition and removal of the existing superstructure and portions of the existing reinforced concrete abutments & piers and construction of a new steel multi-girder bridge with reinforced concrete composite deck atop reinforced concrete abutments and piers; as well as roadway approach reconstruction and repaving, curb and sidewalk reconstruction, a new high-quality bicycle facility, streetlighting improvements, ADA accessibility improvements, railroad electric traction (ET) system modification and utility relocations, and other related work.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This project is a component of the County Bridge Line Item (MPMS #95447).
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
UTL | LOC | $477 | $1145 | $0 | $0 | $0 |
UTL | BOF | $1906 | $4578 | $0 | $0 | $0 |
CON | BOF | $1918 | $2973 | $5192 | $7954 | $15474 |
CON | LOC | $120 | $186 | $324 | $497 | $967 |
CON | 183 | $360 | $557 | $973 | $1491 | $2901 |
Program Year Totals: | $4,781 | $9,439 | $6,489 | $9,942 | ||
Total FY25-FY28 Cost: | $30,651 | Total FY25-FY36 Cost: | $49,993 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2021-06-17 |
UTL | Completion of Phase | 2021-12-30 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Start of Phase | 2023-03-17 |
UTL | Plan to Utility Unit | 2023-05-05 |
FD | PS+E to District Contract Management | 2024-06-15 |
CON | Let | 2025-04-24 |
CON | Award Contract | 2025-05-24 |
FD | Completion of Phase | 2025-06-23 |
CON | Start of Phase | 2025-06-23 |
CON | Notice to Proceed | 2025-06-23 |
CON | Physical Work Complete | 2026-06-25 |
CON | Completion of Phase | 2026-08-24 |
CON | Project Agreement End Date | 2027-12-24 |