98041 | Birchrun Road over Birch Run (Bridge) (West Vincent Township, Chester County)
This project will include the removal and replacement of an existing poor condition Bridge in West Vincent Township.
Limits: West Vincent Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | BOF | $634 | $634 | $0 | $0 | $0 |
Program Year Totals: | $634 | $634 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,268 | Total FY25-FY36 Cost: | $1,268 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2018-03-01 |
ROW | Start of Phase | 2018-03-01 |
ROW | Completion of Phase | 2019-02-14 |
UTL | Completion of Phase | 2019-02-14 |
FD | Completion of Phase | 2019-02-14 |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-10-14 |
UTL | Plan to Utility Unit | 2023-10-14 |
FD | Start of Phase | 2023-11-13 |
CON | Start of Phase | 2024-07-22 |
CON | Notice to Proceed | 2024-07-22 |
FD | PS+E to District Contract Management | 2024-08-14 |
CON | Let | 2024-11-07 |
CON | Award Contract | 2024-12-07 |
CON | Physical Work Complete | 2025-11-30 |
CON | Completion of Phase | 2026-01-29 |
CON | Project Agreement End Date | 2027-05-31 |