95447 | County Bridge Line Item (Various)

This line item sets aside funding allocated for county owned bridges that are in need of repair in the DVRPC region. Funds will be broken out and drawn down at the appropriate time for projects that were selected in the fall of 2012 (Round 1), and summer of 2016 (Round 2). Projects were selected for using 20% local match. State or federal shares will be programmed as appropriate.
Woodland Avenue over SEPTA (MPMS #98232) was programed with 100% federal funds, for preliminary engineering, final design, and construction to allow SEPTA to manage the project on behalf of the City of Philadelphia. This project was drawn down in the FY2013 TIP.
Anticipated programming and costs of projects include:
Round 1 (fall 2012 selections):
Bucks County
-Clymer Avenue Bridge over Mill Creek (MPMS #92872), West Rockhill Township,
FD $59,000, CON $1,194,000. Total cost $1,253,000. This is a retro-reimbursement project. Drawn down in FY14 of the FY2013 TIP.
-Branch Road over E. Branch Perkiomen Creek, (MPMS #102666), Bridge #239, Bridge ID # 09700904310239, East Rockhill Twp,
PE $10,000, FD $60,000, Construction $535,000. The total cost of this project is $605,000. This is a retro-reimbursement project. Drawn down in FY15 of the FY2015 TIP.
-Quarry Road over Morris Run, (MPMS #102667), Bridge #244, Bridge ID #09700904210244
PE $5,000, FD $25,000, Construction $335,000. The total cost of this project is $365,000. This is a retro-reimbursement project. Drawn down in FY15 of the FY2015 TIP.
-Strock's Grove Road Bridge over Beaver Creek Bridge (MPMS #98221), Nockamixon Township, PE $300,000. FD $375,000, ROW $90,000, UTL $50,000, CON $2,000,000. The total cost of this project is $2,630,000.
Chester County
-Sunnyside Road Bridge over East Penn Railway (MPMS #78521) in Penn Township FD $120,000, ROW $31,000, CON $1,021,000. The total cost of the project is $1,172,000. This is a retro-reimbursement project. Drawn down in FY14 of the FY2013 TIP.
-Creek Road Bridge over Pickering Creek (MPMS #98223) in Schuylkill Township, PE $300,000, FD $300,000. ROW $75,000, CON $1,904,000. The total cost of this project is $2,579,000.
-Spring City Road over Stony Run (MPMS #98224) in East Pikeland Township, PE $300,000, FD $200,000, ROW $40,000, CON $1,400,000. The total cost of this project is $1,940,000.
Delaware County
-Michigan Avenue over Little Crum Creek (MPMS #98216) in Ridley Township, PE $350,000, FD $250,000, ROW $50,000, UTL $50,000, CON $2,200,000. The total cost of this project is $2,900,000.
-Hilldale Bridge (MPMS #98217) in Lansdowne Borough, PE $410,000, FD $300,000, ROW $50,000, UTL $50,000, CON 2,850,000. The total cost of this project is $3,660,000.
-South Avenue over Muckinipattis Creek (Mulford Bridge) (MPMS #98218) in Glenolden Borough, PE $450,000, FD $300,000, ROW $50,000 UTL $50,000, CON $2,900,000.The total cost of this project is $3,700,000.
Montgomery County
-Butler Pike over Prophecy Creek (MPMS #98225) in Upper Dublin Township,
PE $400,000, FD $300,000, ROW $25,000, UTL $50,000, CON $1,200,000. The total cost of this project is $1,975,000
-Maple Avenue Bridge (MPMS #98226) in Hatfield Township, FD $143,000, CON $432,000. The total cost of this project is $575,000. This is a retro-reimbursement project. Drawn down in FY15 of the FY2015 TIP.
-Allendale Road Bridge (MPMS #98227) in Upper Merion Township FD $350,000, CON $650,000. The total cost of this project is $1,000,000. This is a retro-reimbursement project. Drawn down in FY15 of the FY2015 TIP.
-Store Road Bridge (MPMS #98228) in Lower Salford Township PE $11,000, FD $80,000, CON $300,000. The total cost of this project is $391,000. This is a retro-reimbursement project. Drawn down in FY16 of the FY2015 TIP.
City of Philadelphia
-59th Street over Amtrak (MPMS #98229) PE $3,000,000, FD $2,000,000, UTL/RR $4,100,000, CON $20,000,000. The total cost of this project is $29,100,000, project is BOF eligible;
-Woodland Avenue over SEPTA (MPMS #98232) PE of $480,000, FD $320,000, CON $952,000, CON $10,048,000. The total cost of this project is $10,848,000. Drawn down in FY14 of the FY2013 TIP, and FY18 of the FY2017 TIP.
-Tabor Road over Tacony Creek (MPMS #98230) PE $240,000, FD $600,000, CON $6,000,000. The total cost of this project is $6,840,000.
Round 2 (summer 2016 selections):
MPMS #s will be created once invoices are received by PennDOT.
Bucks County
-Walnut Street Bridge over Perkiomen Creek (CB #13) (MPMS #13248), Perkasie Borough, CON $5,150,000. This is a retro-reimbursement project.
-Frosty Hollow Road over Mill Creek - CB #15 (MPMS #103620), Middletown Township,
PE $25,000, FD $75,000, ROW $25,000, CON $550,000. Total cost $675,000. This is a retro-reimbursement project. Drawn down in FY2017 TIP.
-Mill Creek Road over Martins Creek - CB #220 (MPMS #102598), Falls Township,
PE $41,000, FD $250,000, ROW $50,000, CON $2,464,000. Total cost $2,805,000. This is a retro-reimbursement project.
Chester County
-State Street in Avondale - CB #289 (MPMS #14246), Avondale Borough,
PE $100,000, FD $250,000, ROW $20,000, UTL $150,000 CON $1,800,000. Total cost $2,320,000. This is a retro-reimbursement project.
-Mill Road in Tredyffrin Twp - CB #167 (MPMS #13981), Tredyffrin Township,
Study $150,000, PE $300,000, FD $300,000, ROW $75,000, UTL $100,000, CON $2,000,000. Total cost $2,925,000. This is a retro-reimbursement project.
-Bertolet School Road - CB #196 (MPMS #86271), East Vincent Township,
Study $200,000, PE $450,000, FD $300,000, ROW $75,000, UTL $100,000, CON $2,775,000. Total cost $3,900,000. This is a retro-reimbursement project.
Delaware County
-Paper Mill Road over Darby Creek (Worrall Bridge) - CB #221 (MPMS #TBD), Newtown Township,
Engineering $410,000, ROW $15,000, CON $2,900,000. Total cost $3,325,000. This is a retro-reimbursement project.
-Fox's Bank Bridge - CB #94 (MPMS #TBD), Middletown Township,
Engineering $300,000, ROW $50,000, CON $2,500,000. Total cost $2,850,000. This is a retro-reimbursement project.
Mongtomgery County
-Moreland Avenue over Branch Pennypack Creek - CB #38 (MPMS #TBD), Hatboro Borough,
PE $350,000, FD $200,000, ROW $60,000, UTL $40,000, CON $2,500,000. Total cost $3,150,000. This is a retro-reimbursement project.
-Easton Road over Branch Tacony Creek - CB #268 (MPMS #TBD), Cheltenham Township,
PE $350,000, FD $200,000, ROW $60,000, UTL, $40,000, CON $2,550,000. Total cost $3,200,000. This is a retro-reimbursement project.
-Moyer Road over East Branch Perkiomen Creek - CB #262 (MPMS #TBD), Upper Salford Township,
PE $350,000, FD $250,000, ROW $25,000, UTL, $20,000, CON $4,355,000. Total cost $5,000,000. This is a retro-reimbursement project.
City of Philadelphia
-MLK Drive over Schuylkill River - (MPMS #108129), City of Philadelphia,
PE $960,000, FD $640,000, CON $10,000,000. Total cost $11,600,000.
-Falls Road Bridge over Schuylkill River - (MPMS #108099), City of Philadelphia,
PE $1,200,000, FD $800,000, CON $10,000,000. Total cost $12,000,000.

Limits: Region-wide
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONLOC$1792$741$831$896$7480
CON183$2468$3424$2863$1206$22889
Program Year Totals:$4,260$4,165$3,694$2,102 
Total FY25-FY28 Cost:$14,221Total FY25-FY36 Cost:$44,590 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONStart of Phase2012-04-04
CONCompletion of Phase2014-04-04
CONPhase Approved by PMC
CONPhase on Approved STIP