95429 | US 202 and US 1 Intersection Area Improvements (Chadds Ford Township, Delaware County)
This project is in Concord and Chadds Ford Townships and involves intersection improvements to ease congestion. Improvements include pavement widening, pavement reconstruction and signal upgrades to accommodate an additional northbound US 1 travel lane through the intersection and a double left turn lane for northbound US 202. Other roadway improvements will include landscaped medians throughout the project area; eastbound and westbound left turn lanes and a signalized US 202 pedestrian crossing at the US 202/State Farm Drive/Brandywine Drive intersections; signalized pedestrian crossings at the US 1/Applied Bank Boulevard/State Farm Drive intersection; and elimination of the southbound Route 1 left turn lane at Dickinson Drive. Project CMP commitments include sidewalks, crosswalks, and enhanced bus stop areas in consultation with SEPTA. See DVRPC’s 2013-2014 memorandum on supplemental strategies for details related to this project.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STP | $833 | $833 | $0 | $833 | $0 |
CON | STU | $0 | $0 | $833 | $0 | $0 |
CON | 581 | $208 | $208 | $208 | $208 | $0 |
Program Year Totals: | $1,041 | $1,041 | $1,041 | $1,041 | ||
Total FY25-FY28 Cost: | $4,164 | Total FY25-FY36 Cost: | $4,164 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2014-03-28 |
UTL | Start of Phase | 2014-03-28 |
UTL | Completion of Phase | 2016-03-30 |
ROW | Completion of Phase | 2016-03-30 |
ROW | Phase Approved by PMC | |
FD | 4232 Approved by FHWA | |
UTL | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
FD | Start of Phase | 2022-09-02 |
ROW | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-05-01 |
ROW | Plan to ROW Unit | 2023-05-01 |
FD | PS+E to District Contract Management | 2024-04-15 |
CON | Let | 2024-08-22 |
CON | Award Contract | 2024-09-21 |
FD | Completion of Phase | 2024-10-21 |
CON | Start of Phase | 2024-10-21 |
CON | Notice to Proceed | 2024-10-21 |
CON | Completion of Phase | 2026-04-24 |
CON | Physical Work Complete | 2026-10-23 |
CON | Project Agreement End Date | 2028-04-22 |