95402 | Bridge Program (SEPTA)
This program will replace or rehabilitate SEPTA’s bridges. Rehabilitation/replacement of bridges on rail lines and SEPTA right-of-ways will include culverts, pedestrian bridges, and associated bridge support structures. Currently programmed projects include:
- Chestnut Hill East Regional Rail Line, 5 Bridges (Philadelphia) - $30.00M (Prior Years - FY 2027)
Mile Post 5.04 over Wayne Avenue; Mile Post 5.72 over Logan Street; Mile Post 7.63 over Chew Street; Mile Post 8.90 over Mt. Pleasant Avenue; Mile Post 9.59 over Chresheim Valley Drive
- Chestnut Hill West Regional Rail Line, 7 Bridges (Philadelphia) - $35.00M (Prior Years - FY 2029) Mile Post 0.06 over SEPTA Main Line; Mile Post 0.83 over 22nd Street; Mile Post 1.17 over Hunting Park Avenue; Mile Post 1.26 over CSX Tracks; Mile Post 2.98 over Rittenhouse Street; Mile Post 4.42 over Carpenter Lane; Mile Post 5.67 over Springfield Avenue
- Critical Bridge Program (System wide) - $180.83M (Ongoing). Annual program to rehabilitate or replace bridges throughout the system to restore infrastructure to a state of good repair Bridges programmed for design and/or construction in FY 2025 include but are not limited to:
- Lansdale/Doylestown Line MP 7.34 (Cooks Run Creek, Built 1887), MP 11.62 (Keswick Avenue, Built 1904), MP 11.83 (Easton Road, Built 1928)
- Fox Chase Line MP 7.03 (3rd St., Built 1910)
- Manayunk/Norristown Line MP 3.83 (Allegheny Ave., Built 1939), MP 17.16 (Dekalb St., Built 1931), MP 17.77 (Stoney Creek, Built 1900)
- Media/Elwyn Line MP 10.12 (Small Run, Built 1965), MP 13.81 (Park Ave., Built 1917)
- West Trenton Line MP 31.63 (Delaware & Raritan Canal, Built 1902)
- Mainline-Schuylkill Bridges Duct Bank (Philadelphia) - $10.95M (Prior Years - FY2027)
- Stone Arch Bridges Phase 2 (Multiple Locations) - $18.20M (Prior Years - FY2027)
Lansdale/Doylestown Line MP 4.87 (Built 1915) and Lansdale/Doylestown Line MP 17.31 (Honey Run Creek, Built 1903)
- Norristown High Speed Line Bridge Mile Post 0.15 (Over 69th Street Yard Tracks) - $5.67M (Prior Years - FY 2025)
- Norristown High Speed Line Bridge Mile Post 12.81 (Bridgeport Viaduct) - $35M (Prior Years - FY2027)
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ERC | 5337 | $1903 | $23883 | $23781 | $7298 | $9502 |
ERC | 1514 | $7303 | $19486 | $12455 | $4356 | $149599 |
ERC | LOC | $243 | $649 | $415 | $145 | $4985 |
Program Year Totals: | $9,449 | $44,018 | $36,651 | $11,799 | ||
Total FY25-FY28 Cost: | $101,917 | Total FY25-FY36 Cost: | $266,003 | |||
All costs in thousands. |