93588 | Exton Station (West Whiteland Township, SEPTA)
Phase 1 of this project, completed in 2020, consisted of the construction of high-level platforms with canopies and wind screens; stormwater management improvements; a new station building, new lighting, signage, security features, and passenger amenities. The station facilities are fully ADA accessible. The total cost of Phase 1 was $28.23M.
Phase 2 includes the design and construction of multimodal improvements including the construction of a bus loop with bus shelter. Derived from the recommendations of Bus Revolution, the planned bus circulator loop will promote intermodal access to the station. Phase 2 is estimated to cost $6M (2026 - 2028).
Phase 3 (TBD) will provide for the development and construction of a fully accessible parking expansion. Due to reduced ridership resulting from the COVID-19 pandemic, SEPTA is re-evaluating its station parking project schedules. A schedule for this phase will be determined as ridership returns.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ERC | 5307 | $0 | $98 | $600 | $262 | $0 |
ERC | LOC | $0 | $1 | $5 | $2 | $0 |
ERC | 1514 | $0 | $24 | $145 | $63 | $0 |
Program Year Totals: | $0 | $123 | $750 | $327 | ||
Total FY25-FY28 Cost: | $1,200 | Total FY25-FY36 Cost: | $1,200 | |||
All costs in thousands. |