93105 | State Rd o/Darby Creek (Bridge) (Springfield Township & Upper Darby Township, Delaware County)
This project is a rehabilitation of State Road bridge over Darby Creek. Additionally, this structure should be able to accommodate a multi-use trail along the creek under the bridge. This road segment is included in the Delaware County Bicycle Plan.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: State Road (SR 0001) between Rolling Road and State Road(SR 2026)
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | 185 | $1528 | $0 | $0 | $0 | $0 |
CON | 581 | $0 | $2041 | $3271 | $2280 | $0 |
Program Year Totals: | $1,528 | $2,041 | $3,271 | $2,280 | ||
Total FY25-FY28 Cost: | $9,120 | Total FY25-FY36 Cost: | $9,120 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2017-09-15 |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | PS+E to District Contract Management | 2023-09-15 |
CON | Let | 2023-12-14 |
CON | Award Contract | 2024-01-13 |
CON | Start of Phase | 2024-02-12 |
CON | Notice to Proceed | 2024-02-12 |
FD | Completion of Phase | 2024-02-19 |
CON | Completion of Phase | 2026-09-06 |
CON | Physical Work Complete | 2026-12-15 |
CON | Project Agreement End Date | 2028-06-14 |