92839 | Ridge Pike over Norfolk Southern RR bridge (CB: #257) (Plymouth Township, Montgomery County)
This project will replace and widen county bridge #257 carrying Ridge Pike, a Montgomery County owned arterial, over Norfolk Southern railroad tracks in Plymouth Township between Belvoir Road and Carland Road. The existing bridge over the railroad is poor condition. This is a companion project to MPMS #48175 and #110444.
Limits: PA Turnpike to Carland Road
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU* | $1250 | $625 | $625 | $0 | $0 |
Program Year Totals: | $1,250 | $625 | $625 | $0 | ||
Total FY25-FY28 Cost: | $2,500 | Total FY25-FY36 Cost: | $2,500 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Plan to Utility Unit | 2011-10-14 |
UTL | Start of Phase | 2012-04-09 |
UTL | Phase Approved by PMC | |
UTL | Completion of Phase | 2013-04-08 |
UTL | 4232 Approved by FHWA | |
CON | Phase Approved by PMC | |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Final ROW Clearance | |
CON | 4232 Approved by FHWA | |
CON | Start of Phase | 2023-03-14 |
CON | Let | 2023-04-27 |
CON | Award Contract | 2023-05-27 |
CON | Notice to Proceed | 2023-07-24 |
CON | Completion of Phase | 2025-03-25 |
CON | Physical Work Complete | 2026-05-24 |
CON | Project Agreement End Date | 2027-11-22 |