92808 | Marshall Rd o/ Cobbs Crk (Bridge) (Philadelphia City & Upper Darby Township, Delaware County)
Bridge rehabilitation or replacement of state bridge over Cobbs Creek on Marshall Road between Cobbs Creek Parkway and 69th Street in Upper Darby Township and City of Philadelphia. poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical exclusion clearance.
This road segment is included in the Delaware County Bicycle Plan.
Limits: Between Cobbs Creek Parkway and 69th Street
Delaware County
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STU | $765 | $0 | $0 | $0 | $0 |
FD | 185 | $191 | $0 | $0 | $0 | $0 |
ROW | STU | $0 | $70 | $0 | $0 | $0 |
ROW | 185 | $0 | $17 | $0 | $0 | $0 |
UTL | 185 | $0 | $5 | $0 | $0 | $0 |
UTL | BRIP | $0 | $19 | $0 | $0 | $0 |
CON | BRIP | $0 | $4544 | $1249 | $3200 | $3249 |
CON | 185 | $0 | $1137 | $312 | $800 | $812 |
Program Year Totals: | $956 | $5,792 | $1,561 | $4,000 | ||
Total FY25-FY28 Cost: | $12,309 | Total FY25-FY36 Cost: | $16,370 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Start of Phase | 2013-04-01 |
UTL | Completion of Phase | 2014-04-01 |
ROW | Start of Phase | 2014-04-01 |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Completion of Phase | 2015-04-01 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2023-04-14 |
UTL | Plan to Utility Unit | 2023-06-15 |
ROW | Plan to ROW Unit | 2023-06-15 |
FD | PS+E to District Contract Management | 2024-09-15 |
CON | Let | 2024-12-12 |
CON | Award Contract | 2025-01-11 |
CON | Start of Phase | 2025-02-10 |
CON | Notice to Proceed | 2025-02-10 |
FD | Completion of Phase | 2025-02-10 |
CON | Physical Work Complete | 2026-10-30 |
CON | Completion of Phase | 2026-12-29 |
CON | Project Agreement End Date | 2028-04-29 |