92808 | Marshall Rd o/ Cobbs Crk (Bridge) (Philadelphia City & Upper Darby Township, Delaware County)

Bridge rehabilitation or replacement of state bridge over Cobbs Creek on Marshall Road between Cobbs Creek Parkway and 69th Street in Upper Darby Township and City of Philadelphia. poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical exclusion clearance.
This road segment is included in the Delaware County Bicycle Plan.

Limits: Between Cobbs Creek Parkway and 69th Street Delaware County
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDSTU$765$0$0$0$0
FD185$191$0$0$0$0
ROWSTU$0$70$0$0$0
ROW185$0$17$0$0$0
UTL185$0$5$0$0$0
UTLBRIP$0$19$0$0$0
CONBRIP$0$4544$1249$3200$3249
CON185$0$1137$312$800$812
Program Year Totals:$956$5,792$1,561$4,000 
Total FY25-FY28 Cost:$12,309Total FY25-FY36 Cost:$16,370 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLStart of Phase2013-04-01
UTLCompletion of Phase2014-04-01
ROWStart of Phase2014-04-01
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase Approved by PMC
ROWCompletion of Phase2015-04-01
UTLPhase on Approved STIP
FDPhase on Approved STIP
ROWPhase on Approved STIP
FDStart of Phase2023-04-14
UTLPlan to Utility Unit2023-06-15
ROWPlan to ROW Unit2023-06-15
FDPS+E to District Contract Management2024-09-15
CONLet2024-12-12
CONAward Contract2025-01-11
CONStart of Phase2025-02-10
CONNotice to Proceed2025-02-10
FDCompletion of Phase2025-02-10
CONPhysical Work Complete2026-10-30
CONCompletion of Phase2026-12-29
CONProject Agreement End Date2028-04-29