92641 | Dublin Pike Bridge over Morgan Creek (Richland Township, Bucks County)
This project involves rehabilitating or replacing the Bridge at Dublin Pike over Morgan Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: Richland Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STU | $424 | $0 | $0 | $0 | $0 |
FD | 185 | $106 | $0 | $0 | $0 | $0 |
ROW | STU | $85 | $0 | $0 | $0 | $0 |
ROW | 185 | $21 | $0 | $0 | $0 | $0 |
UTL | STU | $85 | $0 | $0 | $0 | $0 |
UTL | 185 | $21 | $0 | $0 | $0 | $0 |
CON | 185 | $0 | $622 | $375 | $0 | $0 |
CON | BRIP | $0 | $2488 | $1500 | $0 | $0 |
Program Year Totals: | $742 | $3,110 | $1,875 | $0 | ||
Total FY25-FY28 Cost: | $5,727 | Total FY25-FY36 Cost: | $5,727 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Completion of Phase | 2017-03-31 |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
FD | Start of Phase | 2024-08-30 |
UTL | Plan to Utility Unit | 2024-11-15 |
ROW | Plan to ROW Unit | 2024-11-15 |
FD | PS+E to District Contract Management | 2025-11-13 |
CON | Let | 2026-02-12 |
CON | Award Contract | 2026-03-14 |
CON | Notice to Proceed | 2026-04-13 |
CON | Start of Phase | 2026-04-13 |
CON | Completion of Phase | 2026-10-15 |
CON | Physical Work Complete | 2027-10-30 |
UTL | Start of Phase | 2028-09-30 |
ROW | Start of Phase | 2028-09-30 |
CON | Project Agreement End Date | 2029-04-29 |
UTL | Completion of Phase | 2031-10-01 |
ROW | Completion of Phase | 2031-10-01 |