92637 | Pleaant View Road Bridge over Sanatoga Creek (Lower Pottsgrove Township, Montgomery County)
This project involves rehabilitating or replacing the Bridge at Pleasant View Road over Sanatoga Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: North of Linfield Rd and South of Sanatoga Station Rd over Sanatago Crk on Pleasant View Rd
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | BRIP | $3300 | $0 | $0 | $0 | $0 |
Program Year Totals: | $3,300 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $3,300 | Total FY25-FY36 Cost: | $3,300 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2015-12-30 |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2022-10-01 |
UTL | Start of Phase | 2022-10-01 |
UTL | Plan to Utility Unit | 2023-01-02 |
FD | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-01-02 |
UTL | Completion of Phase | 2023-01-30 |
ROW | Completion of Phase | 2023-01-30 |
FD | PS+E to District Contract Management | 2023-08-01 |
CON | Let | 2023-11-02 |
CON | Award Contract | 2023-12-02 |
FD | Completion of Phase | 2024-01-01 |
CON | Start of Phase | 2024-01-01 |
CON | Notice to Proceed | 2024-01-01 |
CON | Completion of Phase | 2024-05-02 |
CON | Physical Work Complete | 2024-11-15 |
CON | Project Agreement End Date | 2026-05-16 |