92554 | Ridge Ave Over Amtrak (Bridge)
This project invoves rehabiltating or replacing Ridge Avenue (.1 mile SE 29th Street; ) over AMTRAK in Philadelphia. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: 0.1 mile SE 29th Street, Philadelphia
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $339 | $0 | $0 | $0 | $0 |
FD | STP | $1358 | $0 | $0 | $0 | $0 |
ROW | STP | $694 | $0 | $0 | $0 | $0 |
ROW | 185 | $174 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $323 | $0 | $0 |
UTL | BRIP | $0 | $0 | $1291 | $0 | $0 |
CON | 185 | $0 | $0 | $320 | $570 | $1959 |
CON | BRIP | $0 | $0 | $1278 | $2278 | $7834 |
Program Year Totals: | $2,565 | $0 | $3,212 | $2,848 | ||
Total FY25-FY28 Cost: | $8,625 | Total FY25-FY36 Cost: | $18,418 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Start of Phase | 2022-02-15 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2024-04-15 |
ROW | Plan to ROW Unit | 2024-05-15 |
FD | PS+E to District Contract Management | 2026-02-12 |
CON | Let | 2026-06-18 |
CON | Award Contract | 2026-07-18 |
FD | Completion of Phase | 2026-08-17 |
CON | Start of Phase | 2026-08-17 |
CON | Notice to Proceed | 2026-08-17 |
CON | Physical Work Complete | 2026-08-23 |
CON | Completion of Phase | 2027-02-28 |
CON | Project Agreement End Date | 2028-02-21 |