92324 | Gov Printz Blvd o/ Conrail (Bridge) (Tinicum Township, Delaware County)
This project involves rehabilitating or replacing the Bridge at Gov Printz Blvd over Conrail. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
This road segment is included in the Delaware County Bicycle Plan.
Limits: Delaware County, Tinicum Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | BRIP | $2798 | $3849 | $1849 | $1825 | $4873 |
Program Year Totals: | $2,798 | $3,849 | $1,849 | $1,825 | ||
Total FY25-FY28 Cost: | $10,321 | Total FY25-FY36 Cost: | $15,194 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2017-10-31 |
UTL | Plan to Utility Unit | |
ROW | Plan to ROW Unit | 2019-06-19 |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | PS+E to District Contract Management | 2023-07-19 |
CON | Let | 2023-10-19 |
CON | Award Contract | 2023-11-18 |
CON | Start of Phase | 2023-12-18 |
FD | Completion of Phase | 2023-12-18 |
CON | Notice to Proceed | 2023-12-18 |
CON | Physical Work Complete | 2026-02-13 |
CON | Completion of Phase | 2026-04-14 |
CON | Project Agreement End Date | 2027-08-14 |