92323 | Wanamaker Ave o/ Darby Ck (Bridge) (Prospect Park Borough & Tinicum Township, Delaware County)
The project consists of the replacement of both the southbound bridge (BMS 23-0420-0031-0000) and the northbound bridge (BMS 23-0420-0030-0000) which carries S.R. 420 over Darby Creek between the Tinicum Township and Prospect Park Borough in Delaware County. Proposed work for the southbound structure includes full replacement of the structure (superstructure and substructure). The existing northbound bridge is a three span prestressed concrete composite adjacent box beam bridge carrying Northbound S.R. 0420 over Darby Creek. Proposed work for the northbound structure includes full replacement of the structure (superstructure and substructure). At the request of Delaware Valley Regional Planning Commission and the Clean Air Council, a Shared Use Path crossing will be constructed under the bridges adjacent to the southern abutments. This path will provide a connection to the adjacent John Heinz Wildlife Refuge. poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical exclusion clearance. This road segment is included on the Delaware County Bicycle Plan.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | BRIP* | $2045 | $5544 | $9486 | $0 | $0 |
Program Year Totals: | $2,045 | $5,544 | $9,486 | $0 | ||
Total FY25-FY28 Cost: | $17,075 | Total FY25-FY36 Cost: | $17,075 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
FD | 4232 Approved by FHWA | |
FD | Start of Phase | 2019-03-15 |
CON | Final ROW Clearance | |
FD | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
FD | PS+E to District Contract Management | 2022-11-15 |
CON | Phase on Approved STIP | |
CON | 4232 Approved by FHWA | |
CON | Final Utility Clearance | |
CON | Let | 2023-03-23 |
CON | Award Contract | 2023-04-22 |
CON | Notice to Proceed | 2023-05-08 |
FD | Completion of Phase | 2023-05-15 |
CON | Start of Phase | 2023-05-15 |
CON | Physical Work Complete | 2026-11-22 |
CON | Project Agreement End Date | 2028-05-22 |
CON | Completion of Phase | 2030-06-09 |