92323 | Wanamaker Ave o/ Darby Ck (Bridge) (Prospect Park Borough & Tinicum Township, Delaware County)

The project consists of the replacement of both the southbound bridge (BMS 23-0420-0031-0000) and the northbound bridge (BMS 23-0420-0030-0000) which carries S.R. 420 over Darby Creek between the Tinicum Township and Prospect Park Borough in Delaware County. Proposed work for the southbound structure includes full replacement of the structure (superstructure and substructure). The existing northbound bridge is a three span prestressed concrete composite adjacent box beam bridge carrying Northbound S.R. 0420 over Darby Creek. Proposed work for the northbound structure includes full replacement of the structure (superstructure and substructure). At the request of Delaware Valley Regional Planning Commission and the Clean Air Council, a Shared Use Path crossing will be constructed under the bridges adjacent to the southern abutments. This path will provide a connection to the adjacent John Heinz Wildlife Refuge. poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical exclusion clearance. This road segment is included on the Delaware County Bicycle Plan.

Limits: Delaware County - Darby Ck is border between Tinicum Township and Prospect Park Boro
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONBRIP*$2045$5544$9486$0$0
Program Year Totals:$2,045$5,544$9,486$0 
Total FY25-FY28 Cost:$17,075Total FY25-FY36 Cost:$17,075 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
FD4232 Approved by FHWA
FDStart of Phase2019-03-15
CONFinal ROW Clearance
FDPhase on Approved STIP
CONPhase Approved by PMC
FDPS+E to District Contract Management2022-11-15
CONPhase on Approved STIP
CON4232 Approved by FHWA
CONFinal Utility Clearance
CONLet2023-03-23
CONAward Contract2023-04-22
CONNotice to Proceed2023-05-08
FDCompletion of Phase2023-05-15
CONStart of Phase2023-05-15
CONPhysical Work Complete2026-11-22
CONProject Agreement End Date2028-05-22
CONCompletion of Phase2030-06-09