90550 | Creamery Road Bridge over Tohickon Creek (Bedminster Township, Bucks County)
This project involves rehabilitating or replacing the Creamery Road and Tohickon Creek. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization. Improvements also include associated roadway approach reconstruction, guiderail and drainage improvements.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Limits: North of Sweetbriar Rd over Tokickon Creek on Creamery Road.
Bedminster Township, Bucks County
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | STP | $297 | $0 | $0 | $0 | $0 |
ROW | 185 | $74 | $0 | $0 | $0 | $0 |
UTL | STP | $0 | $46 | $0 | $0 | $0 |
UTL | 185 | $0 | $12 | $0 | $0 | $0 |
CON | 185 | $0 | $282 | $251 | $251 | $5499 |
Program Year Totals: | $371 | $340 | $251 | $251 | ||
Total FY25-FY28 Cost: | $1,213 | Total FY25-FY36 Cost: | $6,712 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Completion of Phase | 2022-12-30 |
UTL | Start of Phase | 2023-06-01 |
FD | Start of Phase | 2023-10-11 |
UTL | Plan to Utility Unit | 2023-12-18 |
ROW | Plan to ROW Unit | 2023-12-18 |
FD | PS+E to District Contract Management | 2024-10-01 |
CON | Let | 2025-01-09 |
CON | Award Contract | 2025-02-08 |
FD | Completion of Phase | 2025-03-10 |
CON | Notice to Proceed | 2025-03-10 |
CON | Start of Phase | 2025-03-10 |
CON | Physical Work Complete | 2026-03-10 |
CON | Project Agreement End Date | 2027-09-08 |
CON | Completion of Phase | 2027-09-10 |
ROW | Start of Phase | 2030-09-30 |
ROW | Completion of Phase | 2033-10-01 |