88083 | Stoopville Road Improvements - Phase 2 (Lower Makefield Township, Newtown Township, Upper Makefield Township & Wrightstown Township, Bucks County)
This project will construct multiple pedestrian and roadway improvements along Durham Rd, (S.R. 0413), Stoopville Rd, (S.R. 2028), Eagle Rd. (a township road), Washington Crossing Rd. (S.R. 0532), and Highland Rd. (a township road) from the Stoopville Rd./Durham Rd. (S.R. 0413) intersection to the village of Dolington along Washington Crossing Rd. (S.R. 0532). Proposed improvements include:
(1) Traffic control and gateway signs and painting of stop bars along Washington Crossing Rd. from the Washington Crossing Rd./Dolington Rd. intersection to village of Dolington;
(2) 6’ wide pedestrian walking path along the north side of Stoopville Road from east of Rosefield Drive to Eagleton Farms Road/Hemlock Drive; along the south side of Stoopville Road from Eagleton Farms Road/ Hemlock Drive to Eagle Road; continuing along the west side of Eagle Road to Marigold Drive; along the north side of Stoopville Road from Creamery Road to the intersection of Stoopville Road/ Washington Crossing Road; and continuing along the north side of Washington Crossing Road to Highland Road will be completed; the pedestrian walkway will require the extension of an existing pipe culvert beneath Stoopville Rd. between Highland Rd. and Creamery Rd. to allow the walking path to cross over the tributary;
(3) Decorative crosswalks and ADA-compliant curb ramps at 3 intersections: (1) Eagleton Farms Rd./Stoopville Rd.; (2) Stoopville Rd./Washington Crossing Rd.; and (3) Highland Rd./Washington Crossing Rd.;
(4) New traffic signal and widening at the Durham Rd./Stoopville Rd. intersection to provide a left turn lane at the Durham Rd./Stoopville Rd. intersection for vehicles traveling on southbound Durham Rd. to eastbound Stoopville Rd.;
(5) Modification to the existing signal at the Highland Rd./Washington Crossing Rd. intersection to accommodate a right-turn lane on Highland Rd. and improvements that will provide for both left and right turn lanes for vehicles travelling southbound on Highland Rd. to Washington Crossing Rd.;
(6) Relocation of utility poles.
The first phase (S.R. 2028, Section ECF) was constructed in June 2010 (see MPMS #84096). This project has $254,000 earmark funds remaining from a 2008 Appropriations Bill (PA ID #710).
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 581 | $0 | $0 | $0 | $0 | $802 |
ROW | 581 | $0 | $0 | $0 | $0 | $242 |
UTL | 581 | $0 | $0 | $0 | $0 | $263 |
CON | STP | $0 | $0 | $0 | $0 | $4442 |
Program Year Totals: | $0 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $0 | Total FY25-FY36 Cost: | $5,749 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2009-10-15 |
UTL | Start of Phase | 2009-10-15 |
UTL | Completion of Phase | 2016-06-10 |
ROW | Completion of Phase | 2016-09-09 |
ROW | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Start of Phase | 2022-10-17 |
UTL | Plan to Utility Unit | 2023-01-13 |
ROW | Plan to ROW Unit | 2023-01-13 |
FD | PS+E to District Contract Management | 2024-04-25 |
FD | Completion of Phase | 2024-09-23 |