87781 | US 30, Coatesville Downingtown Bypass (CER-Eastern Section) (East Caln Township, Chester County)

This project provides for the final design, right-of-way, utility and construction phases of the Coatesville-Downingtown Bypass Reconstruction - eastern section - by reconstructing and widening the mainline shoulders; replacing and widening the mainline bridge superstructures; constructing new ramps (to complete partial interchanges ); reconstructing, realigning, and lengthening all on and off ramps (to provide storage length for traffic signals and/or ramp metering); and reconstructing arterial overpasses.
The overall corridor construction cost estimate is $784 million. MPMS# 14532 provides for the preliminary design portion of this project and the western section, as well as additional study work to determine the approach for this eastern section. MPMS #s 107551, 107553, and 107554 contains the construction of the western section, originally housed under MPMS# 84884.
Project CMP (Congestion Management Process) commitments include expansion of Intelligent Transportation Systems (ITS) equipment throughout the corridor, signal improvements on parallel arterials, numerous improvements to rail transit stations and services in consultation with SEPTA and Amtrak, improved access to rail stations, sidewalks and other improvements for pedestrians and bicyclists on parallel arterials, investigation of park-and-ride locations, and outreach to employers to promote transportation demand management strategies. See DVRPC’s 2016-2017 memorandum on supplemental strategies for details related to this project.
$125.353M out of an estimated $632.848M (2023 CON estimate of $530M YOE’d to FY29) is programmed for construction beginning in FY29. The construction balance that is not shown in FY29-FY36 is in the Long-Range Plan.

Limits: US 30, from East of Reeceville Rd Interchange to Quarry Rd.
Air Quality Code: 2045M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
PESTP$0$0$3938$3995$0
PESTU$2957$2957$3024$5000$0
FDSTU$0$0$0$1643$29889
FD581$0$0$0$411$7472
ROWSTU$0$0$0$0$4864
ROW581$0$0$0$0$1216
UTLSTU$0$0$0$0$984
UTL581$0$0$0$0$246
CON185$0$0$0$0$119689
CONSTU$0$0$0$0$0
CON581$0$0$0$0$5664
Program Year Totals:$2,957$2,957$6,962$11,049 
Total FY25-FY28 Cost:$23,925Total FY25-FY36 Cost:$193,949 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
ROWStart of Phase2014-06-02
UTLStart of Phase2014-06-02
ROWPhase Approved by PMC
FDPhase Approved by PMC
UTLPhase Approved by PMC
PECompletion of Phase2016-01-15
PEPhase Approved by PMC
PEStart of Phase2013-01-15
ROWCompletion of Phase2019-06-03
CONPhase Approved by PMC
PE4232 Approved by FHWA
UTLCompletion of Phase2020-09-03
FDCompletion of Phase2020-09-03
ROWPhase on Approved STIP
FDPhase on Approved STIP
PEPhase on Approved STIP
PEN. E. P. A. Approval2023-09-15
FDStart of Phase2023-10-15
CONLet2028-03-16
CONAward Contract2028-04-15
CONNotice to Proceed2028-05-15
CONStart of Phase2028-05-15
CONPhysical Work Complete2030-05-31
CONCompletion of Phase2030-07-30
CONProject Agreement End Date2031-11-29