86244 | River Road Bridge over Delaware Canal (Tinicum Township, Bucks County)
This project will provide for the rehabilitation or replacement of the River Road Bridge over the Delaware Canal in Tinicum Township, Bucks County, a Decade of Investment bridge (DOI #2067). The River Road Bridge is poor condition and based on the most recent inspection in November 2016 its condition continues to deteriorate. As a result of this inspection, the bridge’s posted weight was lowered to 15 tons and repairs were made to abutments and guide rail barrier.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: River Road over the Delaware Canal south of the Golden Pheasant Inn to Sand Castle Winery
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $701 | $0 | $0 | $0 | $0 |
ROW | 185 | $0 | $345 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $157 | $0 | $0 |
CON | 185 | $0 | $0 | $417 | $3024 | $0 |
CON | 581 | $0 | $0 | $2692 | $0 | $0 |
Program Year Totals: | $701 | $345 | $3,266 | $3,024 | ||
Total FY25-FY28 Cost: | $7,336 | Total FY25-FY36 Cost: | $7,336 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Start of Phase | 2018-10-01 |
UTL | Start of Phase | 2018-10-01 |
UTL | Completion of Phase | 2019-09-30 |
ROW | Completion of Phase | 2021-09-30 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2024-06-30 |
ROW | Plan to ROW Unit | 2024-09-13 |
UTL | Plan to Utility Unit | 2024-09-13 |
FD | PS+E to District Contract Management | 2026-03-05 |
CON | Let | 2026-06-04 |
CON | Award Contract | 2026-07-04 |
CON | Start of Phase | 2026-08-03 |
CON | Notice to Proceed | 2026-08-03 |
FD | Completion of Phase | 2026-08-10 |
CON | Open to Traffic | 2027-06-30 |
CON | Physical Work Complete | 2027-10-15 |
CON | Completion of Phase | 2027-12-14 |
CON | Project Agreement End Date | 2029-04-14 |