84284 | Doe Run Rd/Buck Run (Bridge) (West Marlborough Township, Chester County)
This project involves rehabilitating or replacing the Bridge at Doe Run Road over Black Run, bordering West Marlborough and East Fallowfiled Townships. The improvement is a breakout of MPMS #88706 for Bridge Rehabilitation in order to process federal authorization.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Chester County
West Marlborough Township
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STU | $530 | $0 | $0 | $0 | $0 |
ROW | 185 | $0 | $164 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $113 | $0 | $0 |
CON | 185 | $0 | $0 | $602 | $1000 | $2000 |
Program Year Totals: | $530 | $164 | $715 | $1,000 | ||
Total FY25-FY28 Cost: | $2,409 | Total FY25-FY36 Cost: | $4,409 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Start of Phase | 2023-10-01 |
UTL | Start of Phase | 2024-03-18 |
ROW | Start of Phase | 2024-03-18 |
UTL | Plan to Utility Unit | 2024-05-01 |
ROW | Plan to ROW Unit | 2024-06-01 |
UTL | Completion of Phase | 2025-03-31 |
FD | PS+E to District Contract Management | 2025-12-01 |
CON | Let | 2026-03-26 |
FD | Completion of Phase | 2026-03-31 |
ROW | Completion of Phase | 2026-03-31 |
CON | Award Contract | 2026-04-25 |
CON | Start of Phase | 2026-05-25 |
CON | Notice to Proceed | 2026-05-25 |
CON | Physical Work Complete | 2027-07-30 |
CON | Completion of Phase | 2027-09-28 |
CON | Project Agreement End Date | 2029-01-27 |