84258 | Pennsylvania Avenue Bridge over Delaware Canal (Morrisville Borough, Bucks County)
This project involves the replacement of the Pennsylvania Avenue Bridge (SR 2073) over the Delaware Canal in Morrisville Borough, Bucks County, Pennsylvania. The existing crossing is a 68-foot long, two-lane, single-span structure with a concrete deck and bituminous wearing surface on multiple rolled steel I-beams with riveted cover plates that are supported by reinforced concrete abutments. The existing structure was built in 1930. This corridor of roadway is currently classified as an urban minor arterial.
Limits: Morrisville Borough, Bucks County
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 185 | $63 | $0 | $0 | $0 | $0 |
ROW | STU | $252 | $0 | $0 | $0 | $0 |
UTL | 185 | $25 | $0 | $0 | $0 | $0 |
UTL | STU | $99 | $0 | $0 | $0 | $0 |
CON | 185 | $398 | $398 | $299 | $299 | $0 |
CON | STU | $1591 | $1591 | $0 | $0 | $0 |
CON | BRIP | $0 | $0 | $796 | $796 | $0 |
Program Year Totals: | $2,428 | $1,989 | $1,095 | $1,095 | ||
Total FY25-FY28 Cost: | $6,607 | Total FY25-FY36 Cost: | $6,607 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Completion of Phase | 2019-07-26 |
UTL | Start of Phase | 2019-08-01 |
ROW | Start of Phase | 2019-08-01 |
ROW | Completion of Phase | 2019-12-31 |
UTL | Completion of Phase | 2019-12-31 |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | 4232 Approved by FHWA | |
FD | Start of Phase | 2022-08-31 |
ROW | Plan to ROW Unit | 2023-03-17 |
UTL | Plan to Utility Unit | 2023-03-17 |
CON | Let | 2024-06-20 |
CON | Award Contract | 2024-07-20 |
CON | Start of Phase | 2024-08-19 |
CON | Notice to Proceed | 2024-08-19 |
FD | PS+E to District Contract Management | 2024-09-06 |
CON | Physical Work Complete | 2026-01-09 |
CON | Completion of Phase | 2026-01-13 |
CON | Project Agreement End Date | 2027-07-10 |