83742 | Keim Street Bridge Over Schuylkill River (Pottstown Borough & North Coventry Township, Montgomery County)
This project is the replacement of the existing bridge carrying South Keim Street over the Schuylkill River with minor approach roadway work. Additionally, there will be widening of Industrial Highway, to accommodate a right lane along the eastbound side and a left turn lane along the westbound side. The project is located in the Borough of Pottstown in Montgomery County and North Coventry Township in Chester County. The bridge is currently closed to traffic. A programmatic agreement has been signed by all parties for the replacement of this structure.
Limits: Over Schuylkill River
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STP* | $2725 | $3005 | $2125 | $645 | $0 |
Program Year Totals: | $2,725 | $3,005 | $2,125 | $645 | ||
Total FY25-FY28 Cost: | $8,500 | Total FY25-FY36 Cost: | $8,500 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2015-04-15 |
ROW | Start of Phase | 2015-04-15 |
UTL | Completion of Phase | 2016-04-15 |
FD | Completion of Phase | 2016-05-16 |
ROW | Phase Approved by PMC | |
FD | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
FD | Start of Phase | 2020-09-15 |
UTL | Plan to Utility Unit | 2020-11-15 |
ROW | Plan to ROW Unit | 2021-06-20 |
UTL | 4232 Approved by FHWA | |
ROW | Completion of Phase | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | PS+E to District Contract Management | 2023-06-14 |
CON | Let | 2023-09-14 |
CON | Start of Phase | 2023-09-25 |
CON | Notice to Proceed | 2023-09-25 |
CON | Award Contract | 2023-10-14 |
CON | Completion of Phase | 2024-02-14 |
CON | Physical Work Complete | 2025-08-30 |
CON | Project Agreement End Date | 2027-02-28 |