82199 |
Construction of medians, green stormwater infrastructure, traffic signals along Cottman Avenue between Castor Avenue and US 1.
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| CON | TAU | $4120 | $80 | $0 | $0 | $0 |
| CON | LOC | $3950 | $0 | $0 | $0 | $0 |
| CON | SPK-NHPP | $0 | $6000 | $0 | $0 | $0 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||