82087 | Systemic Intersection Improvement Program
District 6-0 will advertise a project for “Intersection Safety Implementation Plan” to address the top ranked feasible locations. The district will identify a typical set of improvements for each of the countermeasures from which PennDOT will consider and select the most appropriate, and implement. Prioritization will involve a dual approach - working down the provided 2021 HSNS intersections list, as well as focusing on locations that are on the statewide cluster list. The PENNSHARE GIS map will be utilized to overlay the 2021 HSNS and Penndot Cluster list which will result in the addressing of safety needs on a corridor basis for highest efficiency. The district intends to use this as a tool to track and report the progress. The project is scalable – it will have the flexibility to add/delete locations depending on funding availability.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
PE | sHVRU | $1000 | $0 | $0 | $0 | $0 |
CON | sHVRU | $3000 | $0 | $0 | $0 | $0 |
Program Year Totals: | $4,000 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $4,000 | Total FY25-FY36 Cost: | $4,000 | |||
All costs in thousands. |