82031 | (Chester County)
This project will build several stations originally included in Chester County's current earmark-funded EV charging station project (MPMS #118553) that exceeded that projects budget due to inflation and had to be omitted from the final PS&E package.
These locations include:
The Chester County Government Services Center (GSC)
The Chester County Justice Center parking garage
Springton Manor Park
Henrietta Hankin Library
The charging stations must be redesigned to meet all requirements of the Carbon Reduction Program, and therefore some funding will be needed to modify the engineering work already completed. This includes increasing the number of charging ports per station, along with anticipated additional electrical and utility upgrades.
| Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
|---|---|---|---|---|---|---|
| CON | CRPU | $0 | $1850 | $0 | $0 | $0 |
| FD | CRPU | $0 | $150 | $0 | $0 | $0 |
| Program Year Totals: | $ | $ | $ | $ | ||
| Total FY25-FY28 Cost: | $ | Total FY25-FY36 Cost: | $ | |||
| All costs in thousands. | ||||||