81292 | Frankford Av/Frankford Ck (Bridge) (Philadelphia City)
Bridge rehabilitation or replacement of state bridge over Frankford Creek on Frankford Avenue between Torresdale Avenue and Castor Avenue in Philadelphia. Poor condition bridge breakout project from MPMS #88706.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Between Torresdale Avenue and Castor Avenue
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | BRIP | $2158 | $2158 | $750 | $1500 | $750 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $2,158 | $2,158 | $750 | $1,500 | ||
Total FY25-FY28 Cost: | $6,566 | Total FY25-FY36 Cost: | $7,316 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Start of Phase | 2022-11-01 |
ROW | Plan to ROW Unit | 2022-11-01 |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2022-12-08 |
UTL | Plan to Utility Unit | 2023-02-01 |
UTL | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2023-01-14 |
FD | PS+E to District Contract Management | 2023-11-01 |
UTL | Completion of Phase | 2024-01-15 |
ROW | Completion of Phase | 2024-01-15 |
CON | Let | 2024-01-25 |
CON | Award Contract | 2024-02-24 |
CON | Start of Phase | 2024-03-25 |
CON | Notice to Proceed | 2024-03-25 |
FD | Completion of Phase | 2024-03-25 |
CON | Physical Work Complete | 2025-03-06 |
CON | Completion of Phase | 2025-05-05 |
CON | Project Agreement End Date | 2026-09-04 |