78757 | JFK Blvd @ 32nd St. o/ SEPTA (30th Street Station) (Bridge) (Philadelphia City)

Rehabilitation of the poor condition; load posted bridge on John F. Kennedy (JFK) Boulevard between Market Street and 30th Street at 32nd Street over SEPTA double track (West Branch).
The current structure is posted for 15 tons based on the substructure condition. The proposed work includes deck and sidewalk repairs/replacement, joint replacement, steel superstructure and substructure repairs/replacement, zone painting of superstructure and substructure, possible bearing replacement, drainage upgrades, and concrete substructure repairs. The project will also include streetscape improvements such as bike lanes and street lighting upgrades. A feasibility study will be undertaken to examine relocation of the I-76 on/off ramps and traffic/pedestrian/transit circulation around 30th Street Station.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This is a breakout from MPMS #69828.

Limits: Between Market Street and 30th Street at 32nd Street over SEPTA double track (West Branch).
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
UTL185$5002$7776$10085$2069$0
CONBRIP$0$0$2188$2942$6000
CONNHPP$0$5565$0$0$0
CON185$0$1391$547$736$1500
Program Year Totals:$5,002$14,732$12,820$5,747 
Total FY25-FY28 Cost:$38,301Total FY25-FY36 Cost:$45,801 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLPhase Approved by PMC
CONPhase Approved by PMC
UTLStart of Phase2019-06-15
UTLCompletion of Phase2019-11-14
UTLPhase on Approved STIP
CONPhase on Approved STIP
UTLPlan to Utility Unit2023-03-15
CONLet2025-01-16
CONAward Contract2025-02-15
CONStart of Phase2025-03-17
CONNotice to Proceed2025-03-17
CONCompletion of Phase2025-11-25
CONPhysical Work Complete2027-05-25
CONProject Agreement End Date2028-11-22