78757 | JFK Blvd @ 32nd St. o/ SEPTA (30th Street Station) (Bridge) (Philadelphia City)
Rehabilitation of the poor condition; load posted bridge on John F. Kennedy (JFK) Boulevard between Market Street and 30th Street at 32nd Street over SEPTA double track (West Branch).
The current structure is posted for 15 tons based on the substructure condition. The proposed work includes deck and sidewalk repairs/replacement, joint replacement, steel superstructure and substructure repairs/replacement, zone painting of superstructure and substructure, possible bearing replacement, drainage upgrades, and concrete substructure repairs. The project will also include streetscape improvements such as bike lanes and street lighting upgrades. A feasibility study will be undertaken to examine relocation of the I-76 on/off ramps and traffic/pedestrian/transit circulation around 30th Street Station.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
This is a breakout from MPMS #69828.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
UTL | 185 | $5002 | $7776 | $10085 | $2069 | $0 |
CON | BRIP | $0 | $0 | $2188 | $2942 | $6000 |
CON | NHPP | $0 | $5565 | $0 | $0 | $0 |
CON | 185 | $0 | $1391 | $547 | $736 | $1500 |
Program Year Totals: | $5,002 | $14,732 | $12,820 | $5,747 | ||
Total FY25-FY28 Cost: | $38,301 | Total FY25-FY36 Cost: | $45,801 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2019-06-15 |
UTL | Completion of Phase | 2019-11-14 |
UTL | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-03-15 |
CON | Let | 2025-01-16 |
CON | Award Contract | 2025-02-15 |
CON | Start of Phase | 2025-03-17 |
CON | Notice to Proceed | 2025-03-17 |
CON | Completion of Phase | 2025-11-25 |
CON | Physical Work Complete | 2027-05-25 |
CON | Project Agreement End Date | 2028-11-22 |