78617 | PA 41 over White Clay Creek (Avondale Borough, Chester County)
This project will rehabilitate and restore a bridge on PA 41 over White Clay Creek in Avondale Borough.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Avondale Borough
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
PE | 185 | $119 | $0 | $0 | $0 | $0 |
PE | STP | $478 | $0 | $0 | $0 | $0 |
FD | STP | $594 | $0 | $0 | $0 | $0 |
FD | 185 | $149 | $0 | $0 | $0 | $0 |
ROW | STP | $1018 | $0 | $0 | $0 | $0 |
ROW | 185 | $255 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $0 | $90 | $0 | $0 |
UTL | STP | $0 | $0 | $360 | $0 | $0 |
CON | 185 | $0 | $0 | $1000 | $4628 | $0 |
Program Year Totals: | $2,613 | $0 | $1,450 | $4,628 | ||
Total FY25-FY28 Cost: | $8,691 | Total FY25-FY36 Cost: | $8,691 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Start of Phase | 2019-10-10 |
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
PE | 4232 Approved by FHWA | |
PE | Completion of Phase | 2024-10-15 |
PE | N. E. P. A. Approval | 2024-09-15 |