70231 | Swanson Street Reconstruction (Philadelphia City)

Reconstruction of the existing roadway to provide a new roadway surface, including footway, medians and curbs, a new high-qulaity bicycle facility, new drainage and stormwater improvements (including GSI where appropriate), street lighting, pavement markings, landscaping and a new signal at the Snyder Avenue intersection.

Limits: Delaware Avenue to Oregon Avenue
Air Quality Code: S10

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONLOC$0$986$736$486$1736
CONSTU$0$0$0$1945$5000
CONSTP$0$3945$2945$0$1945
Program Year Totals:$0$4,931$3,681$2,431 
Total FY25-FY28 Cost:$11,043Total FY25-FY36 Cost:$19,724 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
FDCompletion of Phase2011-07-15
ROWPhase Approved by PMC
FDPhase Approved by PMC
ROWStart of Phase2021-04-01
ROW4232 Approved by FHWA
FD4232 Approved by FHWA
FDStart of Phase2021-02-06
CONPhase on Approved STIP
FDPhase on Approved STIP
ROWPhase on Approved STIP
ROWCompletion of Phase2022-04-01
ROWPlan to ROW Unit2025-08-15
FDPS+E to District Contract Management2025-10-15
CONLet2026-01-15
CONAward Contract2026-02-16
CONStart of Phase2026-03-19
CONNotice to Proceed2026-03-19
CONPhysical Work Complete2028-01-15
CONProject Agreement End Date2029-07-15
CONCompletion of Phase2031-05-02