70231 | Swanson Street Reconstruction (Philadelphia City)
Reconstruction of the existing roadway to provide a new roadway surface, including footway, medians and curbs, a new high-qulaity bicycle facility, new drainage and stormwater improvements (including GSI where appropriate), street lighting, pavement markings, landscaping and a new signal at the Snyder Avenue intersection.
Limits: Delaware Avenue to Oregon Avenue
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | LOC | $0 | $986 | $736 | $486 | $1736 |
CON | STU | $0 | $0 | $0 | $1945 | $5000 |
CON | STP | $0 | $3945 | $2945 | $0 | $1945 |
Program Year Totals: | $0 | $4,931 | $3,681 | $2,431 | ||
Total FY25-FY28 Cost: | $11,043 | Total FY25-FY36 Cost: | $19,724 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Completion of Phase | 2011-07-15 |
ROW | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
ROW | Start of Phase | 2021-04-01 |
ROW | 4232 Approved by FHWA | |
FD | 4232 Approved by FHWA | |
FD | Start of Phase | 2021-02-06 |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Completion of Phase | 2022-04-01 |
ROW | Plan to ROW Unit | 2025-08-15 |
FD | PS+E to District Contract Management | 2025-10-15 |
CON | Let | 2026-01-15 |
CON | Award Contract | 2026-02-16 |
CON | Start of Phase | 2026-03-19 |
CON | Notice to Proceed | 2026-03-19 |
CON | Physical Work Complete | 2028-01-15 |
CON | Project Agreement End Date | 2029-07-15 |
CON | Completion of Phase | 2031-05-02 |