69909 | Willits Road Bridge Over Wooden Bridge Run (Philadelphia City)
This project involves rehabilitating or replacing the bridge carrying Willits Road (S.R. 1011) over Wooden Bridge Run in the City of Philadelphia. The purpose of the project is to extend the service life of the existing structure. The existing structure has severely rusted components, large open spalls exposing rusted reinforced steel, and cracks with efflorescence. Work will include replacing or rehabilitating the existing superstructure and reinforced concrete overlay. The project could also include upgrades to the guiderail approaches.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: Over Wooden Bridge Run
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 185 | $1061 | $0 | $0 | $0 | $0 |
ROW | 185 | $338 | $0 | $0 | $0 | $0 |
UTL | 185 | $0 | $580 | $0 | $0 | $0 |
CON | 185 | $0 | $1631 | $1000 | $2517 | $3432 |
Program Year Totals: | $1,399 | $2,211 | $1,000 | $2,517 | ||
Total FY25-FY28 Cost: | $7,127 | Total FY25-FY36 Cost: | $10,559 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Start of Phase | 2009-08-15 |
FD | Cash Flow End | 2009-12-15 |
FD | Cash Flow Start | 2010-12-15 |
UTL | Start of Phase | 2010-12-15 |
UTL | Completion of Phase | 2016-08-03 |
ROW | Completion of Phase | 2016-09-02 |
CON | Phase Approved by PMC | |
ROW | Plan to ROW Unit | 2022-07-15 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Start of Phase | 2023-10-15 |
UTL | Plan to Utility Unit | 2024-07-15 |
CON | Completion of Phase | 2024-08-30 |
FD | PS+E to District Contract Management | 2024-09-16 |
CON | Let | 2025-02-13 |
CON | Award Contract | 2025-03-19 |
CON | Notice to Proceed | 2025-04-18 |
FD | Completion of Phase | 2025-04-18 |
CON | Start of Phase | 2025-04-18 |
CON | Physical Work Complete | 2026-08-15 |
CON | Project Agreement End Date | 2028-02-13 |