69823 | Rosedale Road Bridge over Unami Creek (Milford Township, Bucks County)
This project is in Bucks County, Milford Township, on Rosedale Road (SR 4059) over a Branch of Unami Creek. The project involves two bridges on Rosedale Road (SR 4059) that are approximately 350 -feet apart. The first bridge is a single span reinforced concrete slab structure with a span length of 13- feet (BARKY 7433). The second bridge is a single span reinforced concrete stringer/girder structure with a span length of 29-feet (BARKY 7434).
The project involves the removal and replacement of the first bridge (BRKEY 7433), rehabilitation or replacement of the second bridge (BARKY 7434), reconstruction of the approach roadways and the roadway between the two structures, drainage improvements as needed, and installation of new guide rail as required.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU | $861 | $861 | $0 | $0 | $0 |
CON | 185 | $215 | $215 | $0 | $0 | $0 |
Program Year Totals: | $1,076 | $1,076 | $0 | $0 | ||
Total FY25-FY28 Cost: | $2,152 | Total FY25-FY36 Cost: | $2,152 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Start of Phase | 2018-08-01 |
UTL | Start of Phase | 2018-08-15 |
ROW | Completion of Phase | 2019-06-19 |
UTL | Completion of Phase | 2019-06-19 |
FD | Completion of Phase | 2019-06-19 |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2022-12-20 |
FD | Start of Phase | 2022-12-20 |
UTL | Plan to Utility Unit | 2022-12-20 |
CON | Phase on Approved STIP | |
FD | PS+E to District Contract Management | 2024-03-20 |
CON | Let | 2024-12-12 |
CON | Award Contract | 2025-01-11 |
CON | Start of Phase | 2025-02-10 |
CON | Notice to Proceed | 2025-02-10 |
CON | Physical Work Complete | 2027-09-01 |
CON | Project Agreement End Date | 2029-03-01 |
CON | Completion of Phase | 2029-06-22 |