❮ Back

69823 | Rosedale Road Bridge over Unami Creek (Milford Township, Bucks County)

This project is in Bucks County, Milford Township, on Rosedale Road (SR 4059) over a Branch of Unami Creek. The project involves two bridges on Rosedale Road (SR 4059) that are approximately 350 -feet apart. The first bridge is a single span reinforced concrete slab structure with a span length of 13- feet (BARKY 7433). The second bridge is a single span reinforced concrete stringer/girder structure with a span length of 29-feet (BARKY 7434).
The project involves the removal and replacement of the first bridge (BRKEY 7433), rehabilitation or replacement of the second bridge (BARKY 7434), reconstruction of the approach roadways and the roadway between the two structures, drainage improvements as needed, and installation of new guide rail as required.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Rosedale Road in Milford Twp
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
CONSTU$861$861$0$0$0
CON185$215$215$0$0$0
Program Year Totals:$1,076$1,076$0$0 
Total FY25-FY28 Cost:$2,152Total FY25-FY36 Cost:$2,152 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
ROWStart of Phase2018-08-01
UTLStart of Phase2018-08-15
ROWCompletion of Phase2019-06-19
UTLCompletion of Phase2019-06-19
FDCompletion of Phase2019-06-19
UTLPhase Approved by PMC
FDPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase on Approved STIP
FDPhase on Approved STIP
ROWPhase on Approved STIP
ROWPlan to ROW Unit2022-12-20
FDStart of Phase2022-12-20
UTLPlan to Utility Unit2022-12-20
CONPhase on Approved STIP
FDPS+E to District Contract Management2024-03-20
CONLet2024-12-12
CONAward Contract2025-01-11
CONStart of Phase2025-02-10
CONNotice to Proceed2025-02-10
CONPhysical Work Complete2027-09-01
CONProject Agreement End Date2029-03-01
CONCompletion of Phase2029-06-22