64795 | Belmont Rd/Rock Hill Rd Widening: I-76 Ramps to Rock Hill Road (Lower Merion Township, Montgomery County)
Widen Belmont Avenue to provide additional lanes, from two to four lanes, intersection improvements and streetscape improvements; replace railroad overpass from from I-76 to Rock Hill Road. This project will also include improvements at the adjacent intersection of Conshohocken State Road and Rock Hill Road.
Project CMP (Congestion Management Process) commitments include signal upgrades, safety treatments, improvements for bicyclists and pedestrians, and turning movement enhancements. See DVRPC’s 2009 memorandum on supplemental strategies for details related to this project.
$21.214M out of an estimated $69M (2023 CON estimate of $46.739M) is programmed for construction in FY36. The construction balance that is not shown in FY36 is in the Long-Range Plan.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | STU | $875 | $0 | $0 | $0 | $0 |
CON | BRIP | $0 | $0 | $0 | $0 | $21214 |
Program Year Totals: | $875 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $875 | Total FY25-FY36 Cost: | $22,089 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Start of Phase | 2019-08-07 |
ROW | 4232 Approved by FHWA | |
ROW | Plan to ROW Unit | 2019-08-15 |
ROW | Completion of Phase | 2020-09-30 |
ROW | Phase on Approved STIP | |
ROW | Plan to Central Office | |
CON | Let | 2024-02-15 |
CON | Award Contract | 2024-03-15 |
CON | Start of Phase | 2024-04-15 |
CON | Notice to Proceed | 2024-04-15 |
CON | Open to Traffic | 2025-12-31 |
CON | Physical Work Complete | 2026-10-15 |
CON | Completion of Phase | 2026-10-15 |
CON | Project Agreement End Date | 2028-04-14 |