64778 | State Road Reconstruction (Bristol Township, Bucks County)
The project is located in Croydon, within Bristol Township, Bucks County. The scope of the project entails full depth pavement reconstruction for approximately 2.2 miles of SR 2002 (State Road) from the bridge crossing the Neshaminy Creek (eastern abutment) to the intersection with SR 0413 (New Rodgers Road).
The main purpose of the State Road Rehabilitation Project is to repair/replace the existing deteriorated pavement and to improve stormwater drainage. Curbing (to control and provide safe access and manage drainage), shoulder widening, addition of left turn lanes at State Road and Cedar Avenue (SR 2011) and traffic signal upgrades are also proposed.
Specifically, the existing 11-foot travel lanes will be widened to a 14-foot eastbound lane and a 12-foot westbound lane/8-foot parking lane (curb both directions) for the western 1.6 miles. Further east, the roadway will be widened to a 12-foot lane with 8-foot shoulder each direction. Adjustments to cross slopes and vertical profile will improve drainage.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
FD | 581 | $1000 | $0 | $0 | $0 | $0 |
ROW | TOLL | $0 | $0 | $0 | $0 | $0 |
ROW | STU | $2476 | $0 | $0 | $0 | $0 |
UTL | 581 | $0 | $0 | $0 | $0 | $3294 |
CON | 581 | $0 | $0 | $0 | $0 | $32980 |
Program Year Totals: | $3,476 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $3,476 | Total FY25-FY36 Cost: | $39,750 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2005-04-15 |
ROW | Start of Phase | 2005-04-15 |
FD | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
UTL | 4232 Approved by FHWA | |
FD | Start of Phase | 2006-03-10 |
FD | Cash Flow Start | 2007-05-18 |
ROW | Cash Flow Start | 2016-01-08 |
UTL | Cash Flow Start | 2016-01-08 |
ROW | Cash Flow End | 2016-02-08 |
FD | Cash Flow End | 2016-10-15 |
CON | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-06-15 |
ROW | Plan to ROW Unit | 2023-06-15 |
FD | PS+E to District Contract Management | 2024-02-07 |
CON | Let | 2024-06-20 |
CON | Award Contract | 2024-11-16 |
FD | Completion of Phase | 2024-12-15 |
CON | Start of Phase | 2024-12-15 |
CON | Notice to Proceed | 2024-12-15 |
CON | Physical Work Complete | 2026-07-29 |
CON | Completion of Phase | 2027-01-26 |
CON | Project Agreement End Date | 2028-01-27 |