64220 | US 422 Expressway Reconstruction (M03) (North Coventry Township, Chester County)
Reconstruction of approximately one mile of expressway including one bridge carrying SR 0422 over Ramp GH at the SR 0724 Interchange; and one bridge carrying Keim Street over SR 0422. The Keim Street Bridge will provide 16’-6” of vertical clearance with SR 0422. SR 0422 horizontal radii will be increased to meet current design standards including stopping sight distance as well as increased shoulder widths and vertical clearance. SR 0422 will be reconstructed with a 9 foot left shoulder, 2-12 foot lanes, and a 12 foot right shoulder in each direction of travel. A concrete glare screen will be provided for physical separation between eastbound and westbound traffic. Acceleration and deceleration lanes at Keim Street Interchange and PA 724 Interchange will be improved to meet current design standards. Also see MPMS #s14698, 16738, 64222, 66986, and 84308.
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | 581 | $0 | $656 | $0 | $0 | $0 |
ROW | NHPP | $0 | $2623 | $0 | $0 | $0 |
UTL | NHPP | $0 | $0 | $0 | $0 | $608 |
UTL | 581 | $0 | $0 | $0 | $0 | $152 |
CON | STP | $0 | $0 | $0 | $0 | $9042 |
CON | NHPP | $0 | $0 | $0 | $0 | $71368 |
CON | 581 | $0 | $0 | $0 | $0 | $25472 |
CON | STU | $0 | $0 | $0 | $0 | $20470 |
Program Year Totals: | $0 | $3,279 | $0 | $0 | ||
Total FY25-FY28 Cost: | $3,279 | Total FY25-FY36 Cost: | $130,391 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
ROW | Start of Phase | 2006-03-15 |
UTL | Start of Phase | 2006-03-15 |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Completion of Phase | 2009-02-15 |
ROW | Completion of Phase | 2009-08-15 |
FD | Completion of Phase | 2012-02-15 |
FD | Phase Approved by PMC | |
FD | Start of Phase | 2021-07-15 |
FD | Phase on Approved STIP | |
FD | 4232 Approved by FHWA | |
UTL | Plan to Utility Unit | 2023-06-30 |
ROW | Plan to ROW Unit | 2023-12-15 |
CON | Completion of Phase | 2024-06-23 |
FD | PS+E to District Contract Management | 2025-12-16 |
CON | Let | 2027-06-24 |
CON | Award Contract | 2027-07-15 |
CON | Notice to Proceed | 2027-08-16 |
CON | Start of Phase | 2027-08-16 |
CON | Physical Work Complete | 2029-12-19 |
CON | Project Agreement End Date | 2031-06-19 |