60651 | Substations and Power Improvements (Various, SEPTA)

These projects will replace existing equipment with modern indoor switchgear and state-of-the-art industry safety systems, communications and relay protection systems, and will provide additional power and reliability. Work includes replacing transformers, trolley breakers, feeder switches, substation switchgears and protective relaying. Power infrastructure must also be brought to a state of good repair. This includes replacing catenary systems and upgrading 80+ year old Regional Rail infrastructure. Additional power improvements will be undertaken as part of the Infrastructure Safety Renewal Program (ISRP) MPMS #90497.
Currently programmed substation and power projects include:
Multimodal Substation Overhaul Program:
- Supervisory Control and Data Acquisition (SCADA) System and Network Upgrade - $18.50M (Prior Years – FY 2029)
- Substation Design and Equipment Purchase - $28.23M (Prior Years – FY 2026)
Power Program:
- 30th Street West Catenary Replacement - $77.00M (Prior Years – FY 2028)
- RRD Automated Wire Scan - $340K (Prior Years – FY 2025)
Railroad Substation:
- Railroad Substation 18th Street Switching Station - $13M (FY 2028 – FY 2032)
- Railroad Substation Brill - $12.8M (FY 2027 – FY 2030)
- Railroad Substation Cresheim Valley - $25.79M (FY 2026 – FY 2029)
- Wayne Junction Static Frequency Converters #1-4 - $101.72M (Prior Years – FY 2028)
- Railroad Substation Woodbourne - $23.79M (Prior Years - FY2028)
Transit Substations Program:
- Transit Substation Ellen - $12.68M (FY 2027 – FY 2029)
- Transit Substation Market - $15M (Prior Years - FY2029)
- Transit Substations Park, Broad, Louden, Castor - $41.65M (Prior Years - FY2029)
- Transit Substation Ranstead - $12.68M (FY 2029 - FY 2032)
- Transit Substation Program - $114.94M (FY 2030 - FY 2036)

Limits: System-wide railroad substations
Air Quality Code: M6

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
ERCLOC$163$217$315$472$3193
ERC1514$4889$6499$9459$14158$95853
ERC5337$15552$24496$28984$34528$128017
Program Year Totals:$20,604$31,212$38,758$49,158 
Total FY25-FY28 Cost:$139,732Total FY25-FY36 Cost:$366,795 
All costs in thousands.

No milestones are available for this project.