48175 | Ridge Pike: Belvoir Road to Chemical Road (Plymouth Township, Montgomery County)
Ridge Pike is a Montgomery County owned principal arterial on the NHS. This project will reconstruct Ridge Pike to provide a center left turn lane to the existing four lane cross-section. Work includes full-depth pavement reconstruction and drainage replacement; upgrading and adding new traffic signals; fiber optic traffic signal interconnections; new sidewalks; and improved transit stops. The overall project extends from the Pennsylvania Turnpike to Chemical Road. Two new bridges over the Turnpike and Norfolk Southern Railroad tracks are proposed under companion projects, MPMS #92839 and #110444, which will be let and constructed concurrently with MPMS #48175.
Limits: Belvoir Road to Chemical Road
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | STU* | $750 | $750 | $0 | $0 | $0 |
Program Year Totals: | $750 | $750 | $0 | $0 | ||
Total FY25-FY28 Cost: | $1,500 | Total FY25-FY36 Cost: | $1,500 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Start of Phase | 2023-04-19 |
CON | Let | 2023-04-27 |
CON | Award Contract | 2023-05-27 |
CON | Notice to Proceed | 2023-07-24 |
CON | Physical Work Complete | 2026-06-21 |
CON | Completion of Phase | 2026-08-20 |
CON | Project Agreement End Date | 2027-12-20 |