48172 | PA 23 Moore to Allendale and Trout Crk Rd Bridge (Upper Merion Township, Montgomery County)

Replace poor condition, functionally obsolete, weight restricted (26 tons) bridge on a new alignment to eliminate a 90 degree turn on the western end of the bridge and adjacent stop controlled intersection due to sight distance of Mancill Mill Road intersection. New bridge and roadway between Moore Road and Vandenberg Road will be two lanes westbound and one lane eastbound.

Limits: Moore Rd to Geerdes Blvd
Air Quality Code: 2035M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDSTU$1013$0$0$0$0
ROW581$101$0$0$0$0
ROWSTU$405$0$0$0$0
UTLSTU$0$0$0$526$0
UTL581$0$0$658$658$0
CON185$0$0$0$0$19898
Program Year Totals:$1,519$0$658$1,184 
Total FY25-FY28 Cost:$3,361Total FY25-FY36 Cost:$23,259 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
ROWStart of Phase2005-02-15
UTLPhase Approved by PMC
FDCompletion of Phase2017-04-17
ROWCompletion of Phase2017-11-15
FD4232 Approved by FHWA
UTL4232 Approved by FHWA
ROW4232 Approved by FHWA
FDStart of Phase2022-04-15
ROWPhase on Approved STIP
UTLPhase on Approved STIP
FDPhase on Approved STIP
UTLPlan to Utility Unit2023-09-15
ROWPlan to ROW Unit2023-12-15
FDPS+E to District Contract Management2025-07-15
CONLet2026-01-15
CONAward Contract2026-02-17
CONStart of Phase2026-03-17
CONNotice to Proceed2026-03-17
CONCompletion of Phase2027-04-05
CONPhysical Work Complete2027-10-07
CONProject Agreement End Date2029-04-06