48172 | PA 23 Moore to Allendale and Trout Crk Rd Bridge (Upper Merion Township, Montgomery County)
Replace poor condition, functionally obsolete, weight restricted (26 tons) bridge on a new alignment to eliminate a 90 degree turn on the western end of the bridge and adjacent stop controlled intersection due to sight distance of Mancill Mill Road intersection. New bridge and roadway between Moore Road and Vandenberg Road will be two lanes westbound and one lane eastbound.
Limits: Moore Rd to Geerdes Blvd
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | STU | $1013 | $0 | $0 | $0 | $0 |
ROW | 581 | $101 | $0 | $0 | $0 | $0 |
ROW | STU | $405 | $0 | $0 | $0 | $0 |
UTL | STU | $0 | $0 | $0 | $526 | $0 |
UTL | 581 | $0 | $0 | $658 | $658 | $0 |
CON | 185 | $0 | $0 | $0 | $0 | $19898 |
Program Year Totals: | $1,519 | $0 | $658 | $1,184 | ||
Total FY25-FY28 Cost: | $3,361 | Total FY25-FY36 Cost: | $23,259 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
ROW | Start of Phase | 2005-02-15 |
UTL | Phase Approved by PMC | |
FD | Completion of Phase | 2017-04-17 |
ROW | Completion of Phase | 2017-11-15 |
FD | 4232 Approved by FHWA | |
UTL | 4232 Approved by FHWA | |
ROW | 4232 Approved by FHWA | |
FD | Start of Phase | 2022-04-15 |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-09-15 |
ROW | Plan to ROW Unit | 2023-12-15 |
FD | PS+E to District Contract Management | 2025-07-15 |
CON | Let | 2026-01-15 |
CON | Award Contract | 2026-02-17 |
CON | Start of Phase | 2026-03-17 |
CON | Notice to Proceed | 2026-03-17 |
CON | Completion of Phase | 2027-04-05 |
CON | Physical Work Complete | 2027-10-07 |
CON | Project Agreement End Date | 2029-04-06 |