17215 | 70th, 71st, 72nd Streets over Amtrak (Philadelphia City)
Rehabilitation of 70th, 71st and 72nd Street Bridges over rail facilities and upgrades of adjacent intersections.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
The 71st and 72nd St. bridges were previously determined eligible for listing on the National Register of Historic Places.
Limits: over Amtrak
Air Quality Code: S19
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
FD | 183 | $0 | $0 | $0 | $0 | $7379 |
UTL | 183 | $0 | $0 | $0 | $0 | $13048 |
CON | BRIP | $0 | $0 | $0 | $0 | $37056 |
Program Year Totals: | $0 | $0 | $0 | $0 | ||
Total FY25-FY28 Cost: | $0 | Total FY25-FY36 Cost: | $57,483 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Start of Phase | 2022-07-01 |
PE | Phase on Approved STIP | |
PE | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
PE | Start of Phase | 2023-05-30 |
PE | Completion of Phase | 2025-10-01 |
CON | Completion of Phase | 2027-12-30 |
FD | Start of Phase | 2028-09-30 |
UTL | Start of Phase | 2029-09-30 |
FD | Completion of Phase | 2030-10-01 |
UTL | Completion of Phase | 2032-10-01 |