16738 | US 422 Expressway Section M1B (Lower Pottsgrove Township, Montgomery County)
Reconstruct approximately 1.7 miles of expressway (from just west of Porter Road to just east of Park Road) including two (2) bridges carrying SR 0422 over Porter Road and Sanatoga Road and Creek, and two (2) bridges carrying Pleasantview Road and Park Road over SR 0422. Replace and extend one (1) culvert at Sprogels Run, located just east of Porter Road. The expressway will be reconstructed on existing alignment meeting current design standards for horizontal radii, shoulder widths, and vertical clearance.
Also see MPMS #s 14698, 64220, 64222, 84308, and 66986.
Limits: Norfolk Southern RR to Park Rd.
Air Quality Code: S10
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
CON | 581 | $1733 | $1733 | $1733 | $1733 | $13864 |
CON | STU | $0 | $0 | $0 | $0 | $15335 |
CON | NHPP | $6931 | $6931 | $6931 | $6931 | $40113 |
Program Year Totals: | $8,664 | $8,664 | $8,664 | $8,664 | ||
Total FY25-FY28 Cost: | $34,656 | Total FY25-FY36 Cost: | $103,968 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final ROW Clearance | |
CON | Phase on Approved STIP | |
CON | Let | 2023-09-28 |
CON | Award Contract | 2023-10-28 |
CON | Start of Phase | 2023-11-13 |
CON | Notice to Proceed | 2023-11-13 |
CON | Physical Work Complete | 2028-01-17 |
CON | Completion of Phase | 2028-03-17 |
CON | Project Agreement End Date | 2029-07-17 |