❮ Back

16577 | Ridge Pike: Harmon Road to Crescent Avenue (Springfield Township & Whitemarsh Township, Montgomery County)

This project involves full-depth reconstruction of the roadway and drainage system, upgrading and interconnecting traffic signals, new sidewalks, improved transit stops, and adding turn lanes at major intersections such as Butler Pike, Joshua Road, and Crescent Avenue. East of Crescent Avenue, Montgomery County has completed the reconstruction and widening of Ridge Pike as a separate County-funded project.
Project CMP (Congestion Management Process) commitments include signal upgrades, new sidewalk connections, turning movement enhancements, and emergency vehicle signal pre-emption. See DVRPC’s 2010 memorandum on supplemental strategies for details related to this project.

Limits: Harmon Road to Crescent Avenue
Air Quality Code: 2035M

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
ROWSTU$2122$2122$0$0$0
ROWLOC$531$531$0$0$0
UTLSTU$0$1748$0$0$0
UTLLOC$0$437$0$0$0
CONLOC$0$280$530$529$5872
CONSTU$0$1121$2121$2116$23490
Program Year Totals:$2,653$6,239$2,651$2,645 
Total FY25-FY28 Cost:$14,188Total FY25-FY36 Cost:$43,550 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
UTLPhase Approved by PMC
ROW4232 Approved by FHWA
UTL4232 Approved by FHWA
UTLCompletion of Phase
ROWCompletion of Phase
ROWPhase Approved by PMC
ROWPhase on Approved STIP
UTLPlan to Utility Unit2023-05-15
ROWPlan to ROW Unit2023-06-15
CONLet2025-04-24
CONAward Contract2025-05-24
CONStart of Phase2025-06-23
CONNotice to Proceed2025-06-23
CONCompletion of Phase2025-11-02
CONPhysical Work Complete2026-04-30
CONProject Agreement End Date2027-10-29