16577 | Ridge Pike: Harmon Road to Crescent Avenue (Springfield Township & Whitemarsh Township, Montgomery County)
This project involves full-depth reconstruction of the roadway and drainage system, upgrading and interconnecting traffic signals, new sidewalks, improved transit stops, and adding turn lanes at major intersections such as Butler Pike, Joshua Road, and Crescent Avenue. East of Crescent Avenue, Montgomery County has completed the reconstruction and widening of Ridge Pike as a separate County-funded project.
Project CMP (Congestion Management Process) commitments include signal upgrades, new sidewalk connections, turning movement enhancements, and emergency vehicle signal pre-emption. See DVRPC’s 2010 memorandum on supplemental strategies for details related to this project.
Limits: Harmon Road to Crescent Avenue
Air Quality Code: 2035M
Phase | Fund | FY25 | FY26 | FY27 | FY28 | FY29-36 |
---|---|---|---|---|---|---|
ROW | STU | $2122 | $2122 | $0 | $0 | $0 |
ROW | LOC | $531 | $531 | $0 | $0 | $0 |
UTL | STU | $0 | $1748 | $0 | $0 | $0 |
UTL | LOC | $0 | $437 | $0 | $0 | $0 |
CON | LOC | $0 | $280 | $530 | $529 | $5872 |
CON | STU | $0 | $1121 | $2121 | $2116 | $23490 |
Program Year Totals: | $2,653 | $6,239 | $2,651 | $2,645 | ||
Total FY25-FY28 Cost: | $14,188 | Total FY25-FY36 Cost: | $43,550 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | 4232 Approved by FHWA | |
UTL | 4232 Approved by FHWA | |
UTL | Completion of Phase | |
ROW | Completion of Phase | |
ROW | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2023-05-15 |
ROW | Plan to ROW Unit | 2023-06-15 |
CON | Let | 2025-04-24 |
CON | Award Contract | 2025-05-24 |
CON | Start of Phase | 2025-06-23 |
CON | Notice to Proceed | 2025-06-23 |
CON | Completion of Phase | 2025-11-02 |
CON | Physical Work Complete | 2026-04-30 |
CON | Project Agreement End Date | 2027-10-29 |