16408 | Fruitville Road Bridge Over Perkiomen Creek (CB #232) (Upper Hanover Township, Montgomery County)

This project involves rehabilitating or replacing the existing structure that is comprised of a stone masonry viaduct with two, 3-span stone masonry arch spans and 110’-long steel, pin connected, Pratt thru truss span that carries Fruitville Road over the Perkiomen Creek and related flood plain. The bridge is currently closed to traffic.
The final alternative for bridge rehabilitation or replacement will be determined upon federal National Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Over Perkiomen Creek
Air Quality Code: S19

FY2025 TIP for PA Program Years (in Thousands)

PhaseFundFY25FY26FY27FY28FY29-36
FDBOF$628$0$0$0$0
FD183$118$0$0$0$0
FDLOC$39$0$0$0$0
ROWBOF$70$0$0$0$0
ROWLOC$4$0$0$0$0
ROW183$14$0$0$0$0
CONBOF$0$0$1146$1146$3438
CONLOC$0$0$72$72$216
CON183$0$0$215$215$645
Program Year Totals:$873$0$1,433$1,433 
Total FY25-FY28 Cost:$3,739Total FY25-FY36 Cost:$8,038 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FD4232 Approved by FHWA
ROWPhase Approved by PMC
CONPhase Approved by PMC
ROWStart of Phase2005-09-15
FDCompletion of Phase2022-08-15
FDCash Flow End2010-03-15
FDCash Flow Start2008-02-15
FDPhase Approved by PMC
ROWCompletion of Phase2018-05-15
CONAward Contract2022-07-15
CONNotice to Proceed2022-08-15
CONStart of Phase2022-08-15
ROWPhase on Approved STIP
FDPhase on Approved STIP
FDStart of Phase2024-02-14
ROWPlan to ROW Unit2024-12-19
CONCompletion of Phase2025-01-02
FDPS+E to District Contract Management2026-03-16
CONLet2026-06-18
CONPhysical Work Complete2027-06-30
CONProject Agreement End Date2028-12-28